Construction Terms Glossary for Small Contractors
Nailed handles the office paperwork from your texts. Try it free
This is a plain-English glossary of the construction terms a small residential GC runs into every week. Each one gets a short definition, a small example with real numbers where it helps, and a link when there is a deeper page.
Money and payments
What is an allowance?
An allowance is a set amount in the quote for something the client has not picked yet, like tile or a light fixture package. If the real cost comes in higher, the client pays the difference.
Example: the quote carries a $3,000 tile allowance. She picks tile and setting materials that total $3,800. The price goes up $800 (plus your markup, if your contract says so). Write the allowance as its own line so nobody argues about it later (see construction allowances explained). More in the scope of work template.
What is a contingency?
A contingency is a pad held back for surprises, like rot behind a wall. It is usually a percent of the job, and it is spent only if the surprise shows up.
Example: 10% on a $30,000 remodel is $3,000. If you find nothing, it stays in the job as profit or goes back to the client, depending on how you wrote it. Say which, in writing. Contingency is not the same as an allowance: an allowance is a known item with an unknown price, a contingency is an unknown item.
What is a deposit?
A deposit is money the client pays before you start. It covers early costs like materials and permits and shows they are serious. State rules often cap how much you can ask for, so check yours first. Our guide on how much deposit a contractor can ask for goes through it.
Example: 30% down on an $18,000 bathroom is $5,400.
What is a draw?
A draw is one scheduled payment during the job, usually tied to a stage of work. The word comes from drawing money out of the contract total. On a small job "the second draw" means the next payment on the schedule.
Example: a $60,000 addition in four draws: $15,000 at signing, $15,000 at framing done, $15,000 at drywall done, $15,000 at completion. See the contractor payment schedule template.
What is a progress payment?
A progress payment is money the client owes for work done so far. It is the same idea as a draw, but measured by how much is finished instead of by a fixed milestone. Someone has to agree on the percent complete, which is where arguments start. See progress payments and retainage.
Example: the job is 40% done on a $50,000 contract. Progress billing to date is $20,000, minus what you were already paid.
What is retainage?
Retainage is a slice of each payment the client holds back until the job is done. You see it on bigger jobs and on subcontracts. Some states limit it, so check the rule where you work.
Example: 10% retainage on $40,000 of billing holds back $4,000. It gets released after the punch list is closed and the job is accepted. Details in progress payments and retainage.
What is markup?
Markup is the percent you add to your cost to get your price. It is calculated on cost.
Example: cost $10,000, markup 25%, price $12,500. Try your own numbers in the markup and margin calculator.
What is margin?
Margin is the part of the price you keep as profit, shown as a percent of the price. It is calculated on the selling price, which is why it always comes out smaller than the markup.
Example: price $12,500, cost $10,000, profit $2,500. $2,500 / $12,500 = 20% margin. A 20% markup on the same cost gives $12,000, and a 16.7% margin. If you want a 20% margin and you add 20%, you are short. The long version is in general contractor profit margin.
What is overhead?
Overhead is what it costs to run the business that is not tied to one job: insurance, truck, phone, software, your own office time. You still have to pay it when no job is running.
Example: $90,000 a year of overhead on $600,000 of revenue is 15% of revenue. Every quote has to carry it or you are paying to work. See how to calculate contractor overhead.
What is job costing?
Job costing is tracking what each job really cost (labor, materials, subs, fees) against what you quoted. It tells you which jobs made money. See job costing without a spreadsheet.
Example: price $24,000, actual costs $19,200, profit $4,800. That is a 20% margin. If costs were $22,000 you would have a $2,000 job, an 8.3% margin, and you would want to know by week two, not at the end.
Quotes and contracts
What is an estimate?
An estimate is your best guess at the cost. It can move. Say that on the page. The estimate vs quote vs bid vs proposal guide lays out how the four words differ.
What is a quote?
A quote is a specific price for a defined scope that you stand behind. If the client accepts it and the scope does not change, the price holds. Treat it as a promise.
What is a bid?
A bid is a price offered to win a job, often against other contractors. Once it is accepted it works like a quote. Residential GCs use "bid" and "quote" almost interchangeably, which is fine as long as the paper is clear.
What is a proposal?
A proposal is the whole document that carries the scope, the price, the schedule, the payment terms and a place to sign. A signed proposal is usually your contract on a small job. Start from the construction proposal template.
What is a scope of work?
The scope of work is the written list of what you will do. It is the most important part of the quote. A price with no scope is just a number.
Example: "Demo existing tub, install new 60-inch tub, tile surround to 8 feet, 12x12 porcelain, new valve." Anything not on that list is not in the price. See the scope of work template.
What are exclusions?
Exclusions are the things the price does not cover. Write them out. Common ones: permit fees, painting, hidden damage, moving furniture, asbestos or mold work.
Example: "Price excludes electrical panel upgrade, drywall repair outside the work area, and permit fees." A client who read that line cannot say you promised the panel. The construction estimate template has a section for it.
What is a fixed-price contract?
Fixed price means one total for the defined scope, no matter what your cost turns out to be. You carry the risk. If you guessed low, you eat it. If you guessed high, you keep it. See fixed price vs time and materials vs cost-plus.
What is time and materials (T&M)?
Time and materials means the client pays for your hours at an agreed rate plus materials, usually with a markup. The client carries the risk of overrun. Good for repairs and jobs where the scope is unknown.
Example: 40 hours at $65 is $2,600. Materials cost $1,100 with a 15% markup, so $1,265. Total $3,865.
What is cost-plus?
Cost-plus means the client pays your actual costs plus a fee, either a percent or a flat amount. It needs open books, because the client has to trust the costs.
Example: costs of $30,000 plus a 15% fee ($4,500) is $34,500. Note the fee here is a percent of cost, so it is a markup, not a margin.
What is a change order?
A change order is a written, signed change to the price or the scope after the deal. Anything the client adds, removes or swaps that moves the number should go on one before the work happens.
Example: client wants two extra outlets: add $450, one extra day. Both of you sign. No signature, no outlets. Nailed does not make change orders yet. See how to price a change order and the change order template.
On the job
What is a permit?
A permit is the city or county's approval to do regulated work, like electrical, plumbing, structural or a deck. Whoever pulls it, usually the GC, is on the hook for inspections. Who pays for it should be on the quote.
What is a rough-in?
Rough-in is the first stage of plumbing, electrical or HVAC, done inside the walls before drywall closes them. Inspectors often check it before you cover it up. Draws are commonly tied to it: "payment due when rough-in passes."
What is a final inspection?
The final inspection is the last check by the building department after all the work is done. Passing it closes the permit. Many GCs make it a condition of the last payment.
What is substantial completion?
Substantial completion is the point where the client can use the space for its intended purpose, even if small items remain. Contracts define it differently, so read yours. It often starts the warranty clock and can trigger the release of most of the retainage.
Example: the kitchen works, the cabinets and counters are in, but two cabinet doors need adjusting. That is substantial completion with a short list left.
What is a punch list?
A punch list is the final list of small fixes: touch-up paint, a sticking door, a missing outlet cover. You walk it with the client, fix everything and get a sign-off. The link to money is direct: punch list done, then sign-off, then the final payment and any retainage. Use the punch list template.
Example: 14 items on the list, $4,000 of the contract still unpaid. Close all 14 and the $4,000 is due.
What is a warranty?
A warranty is your promise to fix defects in your work for a set period, like one year. It does not cover normal wear, misuse or other people's work. Write the length and the exclusions into the contract. Some states set minimums, so check yours.
What is a callback?
A callback is when you have to go back to a finished job to fix something. Callbacks cost time and fuel and they are rarely billed. Track them. Example: three callbacks at $150 each on a $9,000 job with $1,800 of profit takes $450 of it, a quarter.
Paperwork and tax
What is a lien waiver?
A lien waiver is a signed paper where someone says they have been paid and give up their right to put a lien on the property for that amount. Clients and lenders ask for them with each payment. Conditional waivers take effect when payment clears, unconditional ones take effect on signing. Forms and rules vary by state.
What is a mechanic's lien?
A mechanic's lien is a claim a contractor or supplier can file against a property when they are not paid for work or materials. It has strict deadlines and notice rules that vary by state. Missing a deadline can end the right entirely. If you are owed money and think about a lien, talk to a local attorney early. See also what to do when a homeowner won't pay.
What is a COI?
A COI, a certificate of insurance, is a one-page proof that someone carries insurance. You collect one from every sub before they start, and note when it expires. If an uninsured sub gets hurt on your job, you may end up holding the bill. The subcontractor agreement checklist covers what to ask for.
What is a W-9?
A W-9 is the IRS form where a sub gives you their legal name, address and tax ID. Get it before the first payment, not in January. You need it to file their 1099.
What is a 1099-NEC?
A 1099-NEC is the IRS form you send to a sub and the IRS to report what you paid them for services. For payments made in 2026, the IRS threshold is $2,000 per person for the year. For 2025 payments it was $600. It is due January 31. Payments by card are generally reported by the card processor instead, so rules for those differ. The full checklist is in 1099s for subcontractors. Tax rules change, so confirm the current figures with the IRS or your accountant.
Where Nailed fits
Nailed handles some of the paper behind these words: quotes with the scope, allowances and payment schedule, emailed payment reminders in your name until you log the payment, and receipts filed to the right job so job costing is real. You text it. It does not do change orders yet, lien waivers, contracts for subs or the punch list.
- You: paid the guys 1,000 on Klein
- Nailed: $1,000 labor on the Klein job. Save it?
- You: yes
- Nailed: Saved. Klein is at 22% margin so far.
Learn more on the AI office manager for contractors page. Related pages: payment request messages and payment received messages.
Frequently asked questions
What is the difference between markup and margin?
Markup is the percent you add on top of your cost. Margin is the percent of the final price that is profit. A 25% markup on a $10,000 cost gives a $12,500 price and a 20% margin. Same job, two numbers. Mixing them up is how GCs underprice.
What is the difference between a change order and an allowance?
An allowance is a budget for something not chosen yet, already inside the price. A change order is a signed change to the price or scope after the deal. Going over an allowance usually settles through a change order. Choosing tile that costs more than the allowance is the common case.
Which construction terms should go on every quote?
Scope of work, exclusions, allowances, the payment schedule and how changes get priced. Those five stop most fights. If a client can read your quote and say what is not included, you wrote it well.
Are these definitions legal advice?
No. Words like retainage, lien and substantial completion mean different things in different states and contracts. Use this as a plain-English starting point, then check your contract and ask a local attorney when real money is on the line.