Templates
Change Order Example and Free Template (Filled In)
Nailed turns "they want to add a window" into a change order the client signs on their phone. Try it free
Copy the template below, fill in the brackets, and get it signed before you touch the new work. The change order example (filled in, math checked) comes first, then the procedure, the template and notes on each field.
Download it: Word (.docx) or PDF, or copy the text below.
Change order example: a filled-in bathroom remodel
Here is a complete change order example. A $14,500 bathroom remodel. Halfway in, the homeowner wants a tiled shower niche and nicer wall tile. These are example numbers, not a price list, so use your own rates. The change adds $1,544.40 and two working days, and the new total is written out at the bottom.
CHANGE ORDER #1
Date: March 12 Project: Whitaker bathroom remodel, 48 Pine St. Contractor: Ridgeline Remodeling, 555-0142 Client: Dana Whitaker
ORIGINAL CONTRACT Dated March 1, original price $14,500.00. Previous change orders: none Contract total before this change: $14,500.00
DESCRIPTION OF CHANGE
- Frame, waterproof and tile one recessed niche, 12 x 24 in., in the shower back wall, with metal edge trim.
- Upgrade shower wall tile from the contract tile ($4.25/sq ft) to the 3 x 12 ceramic Ms. Whitaker chose ($9.50/sq ft). 68 sq ft ordered (62 sq ft of wall plus waste).
REASON FOR CHANGE Client request.
COST OF THIS CHANGE Labor, niche: 5 hrs x $65 = $325.00 Labor, extra tile setting time (smaller format): 8 hrs x $65 = $520.00 Materials, niche (backer, waterproofing, trim): $85.00 Materials, tile price difference: 68 sq ft x $5.25 = $357.00 Subcontractor: $0.00 Subtotal: $1,287.00 Markup (20%): $257.40 TOTAL THIS CHANGE: $1,544.40
SCHEDULE IMPACT This change adds 2 working days. Original completion date: March 28 New completion date: March 30
NEW CONTRACT TOTAL Contract total before this change: $14,500.00 This change order: $1,544.40 NEW CONTRACT TOTAL: $16,044.40
PAYMENT TERMS FOR THIS CHANGE $772.20 due on signing. $772.20 due at completion with the final payment. Payment method: check or card
TERMS Work described above will not start until this change order is signed by both parties. All other terms of the original contract stay the same. Pricing is good for 7 days from the date above.
SIGNATURES Client: ______________________ Date: __________ Contractor: __________________ Date: __________
The math: labor is $325 + $520 = $845. Materials are $85 + $357 = $442. Subtotal $1,287. Twenty percent markup is $257.40. The change comes to $1,544.40, and $14,500 + $1,544.40 = $16,044.40. Half of $1,544.40 is $772.20 each. When a number won't split evenly, the extra cent goes on the last payment.
A shorter change order example: hidden rot
Not every change order is a client wish. This one is a hidden condition found on demolition day. Same format, fewer lines.
CHANGE ORDER #2 (amends contract dated March 1, now $16,044.40)
DESCRIPTION OF CHANGE Remove and replace 40 sq ft of rotted subfloor under the toilet, found when the old vanity came out. Reason: hidden condition.
COST OF THIS CHANGE Labor: 6 hrs x $65 = $390.00 Materials (plywood, screws, sealant): $180.00 Subtotal: $570.00 Markup (20%): $114.00 TOTAL THIS CHANGE: $684.00 Schedule impact: adds 1 working day.
NEW CONTRACT TOTAL: $16,044.40 + $684.00 = $16,728.40 Due: $684.00 with the next progress payment. Work starts when both parties sign.
Check: $390 + $180 = $570, 20 percent of $570 is $114, and $570 + $114 = $684.
What is a change order?
It's a written amendment to your original contract. One change to scope, price or schedule, agreed by both sides before anyone does the extra work. It isn't an invoice, and it isn't a quote for a new job. It edits the deal you already have.
What should a change order include?
A number. The contract it amends. A plain description of the change. The cost split into labor, materials and markup. Days added or removed. The new contract total. How the extra money gets paid. Both signatures, dated. The template has every one.
Change order procedure: from request to updated payment schedule
- Stop on the new work. When the client asks for something extra, or you open a wall and find a problem, don't start. Say "I'll send you a price for that."
- Write down the change. Where, what, size, brand, finish, and the reason (client request, hidden condition, code).
- Price it. Labor hours at your rate, materials, any sub, then markup on its own line. Add the days it pushes the finish date.
- Write the new contract total. Old total plus this change, or minus it for a credit.
- Send it for signature. Both parties sign and date before the changed work starts. A signed PDF or an e-signature link both work.
- Update the payment schedule. Say when the extra money is due: on signing, with the next progress payment, or at completion. Change your payment schedule so the draws still add up to the new total.
- File it. Keep the signed copy with the job and number the next one CO #2.
Where can I get a free change order template?
Copy the template below, fill in the brackets and get both signatures before the work starts. It covers the contract it amends, the change, labor, materials, markup, schedule impact, the new total and payment terms. Prefer a file? Download the Word or PDF version at the top of this page.
CHANGE ORDER #[number]
Date: [date] Project: [job name / address] Contractor: [your business name, phone, license # if your state requires one] Client: [client name]
ORIGINAL CONTRACT Dated [date of contract], original price $[amount]. Previous change orders: [none / CO #1 $___ ; CO #2 $___ ] Contract total before this change: $[amount]
DESCRIPTION OF CHANGE [What exactly will be added, removed or swapped. Where. What brand, size or spec. One change per change order if you can.]
REASON FOR CHANGE [Client request / hidden condition found / code or inspector requirement / material unavailable]
COST OF THIS CHANGE Labor: [hours] x $[rate] = $[amount] Materials: $[amount] Subcontractor: $[amount, or 0] Subtotal: $[amount] Markup/overhead and profit ([x]%): $[amount] TOTAL THIS CHANGE: $[amount] (use a minus sign for a credit)
SCHEDULE IMPACT This change adds / removes [number] working days. Original completion date: [date] New completion date: [date]
NEW CONTRACT TOTAL Contract total before this change: $[amount] This change order: $[amount] NEW CONTRACT TOTAL: $[amount]
PAYMENT TERMS FOR THIS CHANGE $[amount] due [on signing / with the next progress payment / at completion]. Payment method: [check, card, transfer]
TERMS Work described above will not start until this change order is signed by both parties. All other terms of the original contract stay the same. Pricing is good for [number] days from the date above.
SIGNATURES Client: ______________________ Date: __________ Contractor: __________________ Date: __________
How do I fill in each field?
Write each field so a stranger could read it cold. The table shows what goes in every field and the mistake that usually shows up there. Four of them cause most of the fights, and they're covered right after the table.
| Field | What to write | Common mistake |
|---|---|---|
| CO number | Count up from 1 per job | Reusing "Change order" with no number, so nobody knows which is which |
| Original contract | Date and price, plus earlier change orders | Leaving out earlier changes, so the total is wrong |
| Description | Where, what, size, brand, finish | "Extra tile work" tells nobody anything |
| Reason | One line: client request, hidden condition, code | Skipping it. When it's a hidden condition, it protects you later |
| Labor | Hours times your rate | Guessing a lump sum you can't explain |
| Materials | Actual cost or the price difference | Charging full price for an upgrade when the base item was already in the bid |
| Markup | Same percent as the original bid, on its own line | Hiding it in the labor number |
| Schedule impact | Whole working days, with new finish date | Writing "TBD". Give your best number |
| New contract total | Old total plus this change | Not writing it at all |
| Payment terms | Amount and when, matching your payment schedule | "Due later" |
| Signatures | Both parties, dated | Starting work on a text that says "ok" |
Four of these cause most of the fights.
Description. Write it so a stranger could build from the page. Size, location, brand, finish. Stay vague and the argument shows up at the end of the job.
Upgrades. Charge the difference, not the full price, when the base item is already in the contract. In the example, the original $4.25 tile is already credited inside the $5.25 difference.
Schedule. A day matters. If the change pushes your finish date and you didn't write it down, you're the one who looks late.
Hidden conditions. Open a wall, find rot? Say so in the reason line, add the date, and take photos for the job file.
Do I need a change order for every change?
Yes, anything that moves price, scope or schedule. Even the small ones. Forty bucks here and sixty there is real money by Friday. One unbilled change took a $48,000 kitchen's net profit from 6.0% to 2.25%. Want less paperwork on the tiny stuff? Write a threshold into the original contract and keep the texts.
Something like "changes under $[x] may be approved by text." The on-site script, timing and pricing rules are in how to get a change order signed before the work starts.
Can a change order be signed electronically?
Generally, yes (checked Oct 2026). The federal ESIGN Act says a signature, contract or other record "may not be denied legal effect, validity, or enforceability solely because it is in electronic form" (15 U.S.C. 7001(a)). Most states also have their own version of the Uniform Electronic Transactions Act. Keep a record of who signed, when, and which version they saw.
How Nailed fits in
Nailed is who you text for the office work. It builds your quote from a voice note, sends it for e-signature and keeps the signed copy. Standalone change orders are coming soon. Until then, a revised quote with the new total goes out and gets e-signed the same way. You tap Send first. The AI doesn't do the math.
- You: Whitaker bath, she wants a shower niche and the better tile. 5 hrs for the niche, 8 more on tile, materials come to 442
- Nailed: Got it. Labor 13 hrs at your $65 rate is $845.00. Materials $442.00. Subtotal $1,287.00. With your usual 20% markup that's $1,544.40, new total $16,044.40. Send a revised quote for her signature?
- You: yes
- Nailed: Sent. She gets a link, no login. I'll tell you the second she signs. Note: formal change orders are coming soon, so this goes out as a revised quote.
- Nailed: Dana signed the revised quote. Signed copy is in the Whitaker job file.
More on how it works is on the how it works page and the AI office manager for contractors page. See pricing for what's included.
Frequently asked questions
Does a change order need to be on paper?
Not always by law. Do it anyway. A signed change order is the first thing you point to when a client disputes a charge. Some states require written changes on home improvement contracts, so check yours or ask a local attorney.
Can the change order be signed on a phone?
Yes, in most cases. Federal law says a signature or contract can't be thrown out just because it's electronic, as long as the signer meant to sign and agreed to do business that way. Keep a record of who signed, when, and which version they saw.
Should I put a markup on a change order?
If your contract allows markup on changes, give it its own line. Bury it in labor or material and you've invited an argument. Use the same markup as the original bid, and say so in the contract before the job starts.
What if the change makes the job cheaper?
Write it as a credit. Put a minus sign on the cost line and subtract it from the contract total. It needs the same signatures as one that adds cost, because you're still changing what you promised to build, and the client should agree to it in writing.