How to Price a Change Order (With a Worked Example)

By Roy, Founder of Nailed. Published . 6 min read.

Nailed turns "they want to add a window" into a change order the client signs on their phone. Try it free

To price a change order, add your direct cost for the new work (labor, materials, subs), add the cost of the disruption it causes, then apply the same markup you use on any job. Write the new total and the new schedule on one page and get it signed before anyone picks up a tool.

How do you price a change order?

Cost it like a small job. Add up what the change costs you, add the disruption, add your markup, and show the total. The client has already seen your numbers once, and they'll compare.

The steps:

  1. Scope in one sentence. What is added, removed or changed.
  2. Labor. Hours times your loaded rate (wages plus taxes, workers' comp, the share of insurance). The labor rate calculator gets you that rate.
  3. Materials. At your cost, with tax and delivery.
  4. Subs. Their written quote, not a phone guess.
  5. Disruption. See below.
  6. Markup. Your normal percentage, on all of it.
  7. Schedule effect. Days added, and how it changes the draws.

A worked example: lights and a doorway

Say a kitchen remodel is a $38,000 fixed-price job. Halfway through, the homeowner wants under-cabinet lighting and the pantry doorway moved 18 inches. The numbers are made up. The arithmetic is checked.

LineHowCost
Labor: framing, drywall, trim14 h x $48 loaded rate$672.00
Materials: lighting kit, wire, lumber, drywall, trimAt cost$310.00
Electrician (sub quote)Written quote$450.00
Direct cost of the change$1,432.00
Disruption: crew waits on the electrician, then returns8 h x $48$384.00
Cost including disruption$1,816.00
Markup 20%$1,816.00 x 0.20$363.20
Change order price$2,179.20

Without the disruption line, the same change would have been $1,432.00 x 1.2 = $1,718.40. The disruption added $460.80 to the price. That's the line people forget, and then they eat it.

Is change order markup the same as profit margin?

No. Markup is the percent you add on top of cost. Margin is the share of the final price you keep. In the example, $363.20 on a price of $2,179.20 is a 16.7% margin, not 20%.

If you want a margin, you can't just add that percent. To keep 20% of the price, you need a 25% markup. This table does the conversion:

Markup on costMargin on price
10%9.1%
20%16.7%
25%20.0%
30%23.1%
50%33.3%

The markup and margin calculator does this in one tap. The profit margin guide covers what's a healthy number. For a sanity check, NAHB's 2024 remodeler data shows a 29.9% gross margin and 6.3% net. The gap between those two is overhead, which is why a margin that sounds big on a change order is mostly spoken for. Not sure what your own overhead is? Here is how to work it out.

Do I add overhead and profit to change orders?

Yes. Overhead doesn't pause because the work is small. Your markup pays the insurance, the truck and your admin hours. Skip it on changes and each one cuts into the job.

If your contract names a markup for changes, use that. If it's silent, use your normal one and say so on the change order. The honest version: "Includes 20% for overhead and profit."

How do I charge for delays and disruption?

Put it on its own line, with a short reason. "Remobilization: crew off site 2 days waiting on the electrician." Clients accept a labeled line more easily than a bigger lump sum they can't read.

What counts:

  • Crew time idle while the change is figured out or ordered
  • A second trip, a second dump run or a second setup
  • Work already done that has to be opened up or redone
  • Added days on the schedule that push your next job

Be fair. Charge hours you actually lose, not hours you wish you had. And if a change adds two days, say the new finish date on the page.

How does a change order change the payment schedule?

The total goes up, so something has to move. You have two clean options. Collect part of the change when it's signed, or add it to the next draw. Pick one and write it down.

In the example, the original schedule is four draws of $9,500. The client signs the change order and pays half now:

ItemAmount
Original contract$38,000.00
Change order$2,179.20
New total$40,179.20
Paid with the change order (50%)$1,089.60
Final draw (was $9,500.00, now $9,500.00 + $1,089.60)$10,589.60

Half up front covers your materials here, and the other half rides on the final draw. On a bigger change, collect more. Don't let it hide in the last payment alone, because that's how a $2,000 change turns into a fight over a $10,000 check. Retainage works the same way, so see progress payments and retainage if your jobs hold some back.

What goes on the change order itself?

Keep it to one page: the description, the price with the breakdown, the added days, the new total, the payment terms, and a signature line for both of you. The change order template has the wording ready to copy. And how to get change orders signed covers the harder part: making sure it happens before the work does.

Where does Nailed fit?

Nailed doesn't make change orders yet. That's coming soon. What it does today is keep the money straight around them. Tell it what you bought for the change and it files the receipt to the right job, so you can see the profit with the change in it. If the change is on a payment schedule, it emails the client the reminder in your name until you log the payment.

Nailed on WhatsApp
  1. You: Picked up lighting kit and wire for Dana's kitchen, 310 at the supply house
  2. Nailed: Filed $310.00 to Dana kitchen. Want the profit so far?

More on the AI office manager for contractors and pricing. Words trip you up? Try the contractor glossary. Pricing the base job? See the construction estimate template.

Frequently asked questions

Can I charge for the time spent pricing a change order?

You can, if you say so before you do it. Pricing a small change for free and charging for a big one that needs drawings or sub visits is a fair rule. Put it in your contract. Then it's a policy, not a surprise on the invoice.

What if the client approves the change verbally?

Treat it as not approved until it's written and signed. A verbal yes turns into 'I never agreed to that price' at the final payment. Text the number back, get it signed, then start. Even a one-line signed change beats a memory.

How do I handle a credit change order?

Same math in reverse. Price the work and materials you no longer do, subtract your direct cost saved, and be honest about what you can't recover: restocking fees, ordered materials, setup already done. Your contract should say whether you keep markup on removed work.

Do I charge the same markup on a change order as on the base job?

Usually, and your contract is the place to say so. Change work is often more expensive to do, because it interrupts a plan. Keep your normal markup and add a separate line for the disruption instead of inflating the percentage.