Tag every expense to a job on the day you spend the money. Write down six things: the job, the vendor, the amount, the date, a category and a photo of the receipt. Then compare each job's total against what you budgeted, every week.
That's the whole system. The rest of this page is how to make it stick when you're standing in a Home Depot aisle with a cart and a crew waiting.
Why track expenses by job instead of by month?
Because margin is a per-job number. Your monthly books tell you the business spent $41,000. They don't tell you the Alvarez bath ate $620 more in materials than you planned. A losing job hides inside a good month.
Deposits make it worse. A client's check lands, the account looks healthy, and you feel fine. But cash in isn't profit. Profit is what's left of the contract price after every cost that belongs to that job. If you don't know the costs per job, you can't know the profit per job.
Tracking by job also fixes your next quote. When you finish a bath and know it really cost $19,211, the next bath estimate stops being a guess. That's the real payoff. The tax benefits are a side effect.
What do you need to record on every expense?
Six fields. Date, vendor and amount are on the receipt. You add the job, the category and the receipt photo. If you're reimbursing a helper or a partner, add a seventh: who paid.
| Field | Example | Why it matters |
|---|---|---|
| Job | Alvarez bath | The whole point. No job, no job cost. |
| Vendor | Home Depot | Lets you find the receipt and spot a vendor that keeps running you over. |
| Amount | $412.18 | Total with tax, as printed. |
| Date | Oct 6 | Lines the cost up with the week of work it belongs to. |
| Category | Materials | Shows where the money went inside the job. |
| Receipt photo | (image) | The proof. More on that below. |
| Paid by (optional) | Marco, his card | So you reimburse the right person once, not twice. |
The IRS says supporting documents for your income and expenses include sales slips, paid bills, invoices, receipts, deposit slips and canceled checks (Publication 583). A phone photo of the receipt, tied to a job, is a clean way to keep that paper. This guide stays on recordkeeping. What you can deduct is a tax question, so ask your CPA and see IRS Publication 535.
Which categories should a small GC use?
Six is enough:
- Materials. Lumber, tile, fixtures, drywall, paint.
- Labor. Your crew's hours on this job, at their loaded rate.
- Subs. Plumber, electrician, tile setter, anyone who sends you an invoice.
- Equipment and rentals. Only what you rented for this job.
- Permits and dumpster. Fees and hauling.
- Fuel and consumables. Blades, tape, screws, caulk, the stuff nobody budgets.
Resist the urge to add more. Every extra category is one more decision at the register, and decisions at the register are where tracking dies. You can always split "materials" later if a category gets big enough to matter.
Labor deserves a note. If you pay yourself, put your own hours in too, at a real rate. Otherwise every job looks more profitable than it was. If you don't know your number, the labor rate calculator walks through it.
How do you do it without a spreadsheet?
You send the receipt the moment you have it. Photo, job name, done. With Nailed, that's a text to the same chat you use for everything else.
- You: [photo of Home Depot receipt]
- You: Alvarez bath
- Nailed: Got it. Home Depot, Oct 6, $412.18. Filing it to the Alvarez bath under materials. Right?
- You: Yep
- Nailed: Saved ✅ $412.18 · Home Depot · Alvarez bath
The amount comes off the receipt, and you see it before it's filed. Nothing about a job's money changes until you confirm, because the assistant never gets to quietly decide what a number is. If the total is wrong, say so and fix it. You can read more about how Nailed works, or see the bigger picture of the AI office manager for contractors.
Later, ask "how am I doing on the Alvarez bath?" and you get the costs so far and the running job profit, built from the costs you've logged against your quote. That's the part a shoebox can't give you.
The method works with any tool. What matters is the habit: capture at the register, not at the kitchen table on Sunday night.
What if you prefer a spreadsheet?
A spreadsheet works fine if you actually fill it in. Make one tab with these columns:
Date | Job | Phase | Vendor | Amount | Category | Paid by | Receipt link
Rules that keep it honest:
- One row per receipt, or per job if the receipt is split.
- Category comes from a dropdown with your six choices. No free typing, or you'll get "Materials", "materials" and "mats".
- Receipt link points to the photo in a folder named for the job.
- Once a week, build a pivot table with Job down the side, Category across the top and the sum of Amount in the middle. That's your job cost report.
- Add a Budget column next to each category total, and a column for the difference.
The weak spot is entry. You'll fill it in at night from a pile of paper, and some receipts will vanish. If that happens more than twice a month, you'll want something on your phone.
How do you handle one receipt for two jobs?
Split it by line. Say the receipt is $236.40: $148.00 of it is the Alvarez bath and $88.40 is the Klein deck. Two rows, one photo, and the amounts must add up to the receipt total. Check it: 148.00 + 88.40 = 236.40.
Do the split the same day, while you can still remember which cans of caulk went where. If you're unsure, put the whole receipt on one job and note the split in plain words. A rough split recorded today beats a perfect one you never get to.
What does a job look like after a month of tracking?
Here's the Alvarez bath, contract price $22,400, at the end of the job. Budget on the left, what actually got logged on the right.
| Line | Budget | Actual | Over |
|---|---|---|---|
| Materials | $6,800.00 | $7,420.00 | $620.00 |
| Subs (plumber, tile) | $5,200.00 | $5,200.00 | $0.00 |
| Labor (96 h budgeted, 112 h actual, at $48) | $4,608.00 | $5,376.00 | $768.00 |
| Dumpster and permit | $700.00 | $700.00 | $0.00 |
| Fuel, consumables | $400.00 | $515.00 | $115.00 |
| Total cost | $17,708.00 | $19,211.00 | $1,503.00 |
Now the margin. Planned profit was $22,400 minus $17,708, which is $4,692.00, or 20.95% of the price. Actual profit was $22,400 minus $19,211, which is $3,189.00, or 14.24%.
A $1,503 slip cost almost seven points of margin. Not one dollar of it showed up in the bank, because the client paid exactly what the contract said. The only way you see it is by tracking costs against the job.
Look at where it came from. Materials ran $620 over (say a vanity upcharge and a second trip for tile). Labor ran 16 hours long. Fuel and consumables ran $115 over, which is the kind of number nobody notices, and it's 29% above the $400 budget. None of these is a disaster alone. Together they took a fifth of your profit.
Tracking doesn't stop the overruns. It tells you early enough to do something, like pricing the extra work. That's the topic of the warning signs that a job is losing money. For what a healthy margin looks like, see the general contractor profit margin guide, or work out the price you needed with the markup and margin calculator.
How long do you keep receipts?
The IRS general rule is three years from when you filed the return. Some cases run longer:
- 3 years if none of the cases below apply.
- 6 years if you left out income and the amount is more than 25% of the gross income on your return.
- 7 years if you claim a bad debt deduction or a loss from worthless securities.
- At least 4 years for employment tax records, counted from when the tax is due or paid, whichever is later.
- Indefinitely if you never filed, or filed a fraudulent return.
Most GCs keep seven years of everything and stop thinking about it. Photos cost nothing to store.
What about overhead and your own time?
Keep them separate. Overhead is the cost of running the business that doesn't belong to one job: insurance, your truck, your phone, software, the office help. Don't try to tag a share of the insurance bill to every receipt. Work out an overhead percentage once a year and apply it when you price.
Your own time is the one people forget. If you spend 30 hours on a bath and pay yourself nothing on the job, the job looks like it made $3,189 when it really made less. Put a rate on your hours, even if you don't pay it out. For the overhead math, the profit margin guide has NAHB's averages, and the labor rate calculator turns wages into a charge-out rate.
If receipts are stacking up because you have no office help, the office manager vs virtual assistant guide lays out what each kind of help costs.
Once receipts land on the right job, compare them to a budget. The job cost sheet template is a filled one-page version, and the job costing guide has a starter list of cost codes and a worked bath job.
Snapping receipts is one part of working from the truck. The guide on running a contractor business from your phone covers the rest, and the subcontractor agreement checklist helps when the receipt is a sub's invoice.
Frequently asked questions
Do I need cost codes to track job expenses?
No. Cost codes are built for big contractors with an accounting department. A one-truck shop does fine with six plain categories: materials, labor, subs, equipment and rentals, permits and dumpster, fuel and consumables. If you can't say which bucket a receipt goes in within five seconds, you have too many buckets.
What if I forget to tag a receipt to a job?
Do a sweep before you leave the site each evening. Pull the receipts out of the truck, the wallet and your camera roll while you still remember what each was for. A receipt from last Tuesday with no job on it is a guess. Tomorrow's version of you won't know either.
Can I track expenses per job and still use QuickBooks?
Yes. They answer different questions. Your books answer what the business spent and owes, and your bookkeeper and your tax return depend on them. The per-job view answers whether this job made money. Keep both. Don't ask the books to do the job view's work.
Do I track my own truck and tools per job?
Usually as overhead, not per job. Your truck, tools, insurance and phone belong in your overhead rate. The exception is a rental, like a lift or a tile saw you rented for this one bathroom. That's a direct cost, so tag it to the job.