Subcontractor Agreement Checklist for Small GCs

By Roy, Founder of Nailed. Published . 6 min read.

Nailed handles the office paperwork from your texts. Try it free

A subcontractor agreement should cover who does what, for how much, by when, with what paper on file, and how it ends. This page is a checklist, not a contract. Run every sub through it before the first payment.

What should be in a subcontractor agreement?

Seven areas: the paper, scope, price and payment, schedule, changes, quality and warranty, and how it ends. A blank in any of them is where trouble starts. The copyable version is below, and the sections after it explain the ones that bite most.

Subcontractor agreement checklist (copy and fill in)

SUBCONTRACTOR AGREEMENT CHECKLIST Job: ____________________ Address: ____________________ Sub (legal name): ____________________ Phone/email: ____________ Date: ____________

PARTIES AND PAPER [ ] Sub's legal name and business type (sole prop, LLC, corp) match the W-9 [ ] Signed W-9 on file BEFORE first payment [ ] License number: ____________ Expires: ____________ (checked with the state/local board) [ ] Certificate of insurance on file. General liability limit: ________ [ ] COI names ME as additional insured [ ] Workers' comp on COI, or sub states in writing they have no employees [ ] COI expiry date: ____________ (reminder set for 2 weeks before)

SCOPE [ ] Scope written in plain lines: ____________________________ [ ] What is NOT included: ____________________________ [ ] Who supplies materials: [ ] sub [ ] me Tools and equipment: sub [ ] Plans/specs/selections attached: ____________

PRICE AND PAYMENT [ ] Price: $__________ [ ] fixed [ ] hourly at $____ [ ] other: ____ [ ] Payments: __% at start, __% at ____________, __% at finish [ ] Invoice due ____ days after sub submits it [ ] Payment tied to: [ ] work done and inspected [ ] my receipt of client payment [ ] neither [ ] Retainage held: ____%, released when ____________ [ ] Lien waiver collected with each payment: [ ] conditional [ ] unconditional

SCHEDULE [ ] Start date: ________ Finish date: ________ [ ] Sub confirms arrival 2 days ahead [ ] What happens if the job is delayed by me / by weather / by the sub: ____________

CHANGES [ ] No extra work without a written, priced change signed by both of us [ ] Change price is agreed BEFORE the work: ____________

WORK QUALITY, CLEANUP, WARRANTY [ ] Code and permit/inspection responsibility: ____________ [ ] Sub cleans up their own debris daily, hauls their waste [ ] Sub fixes defects within ____ days of notice [ ] Warranty on their work: ____ months

ENDING IT [ ] What counts as default: ____________ [ ] Notice to fix: ____ days in writing [ ] I can end the agreement if default isn't fixed; payment for unfinished work: ____ [ ] Sub can end if I don't pay: ____ days notice

SIGNATURES Sub: ______________ Date: ______ Me: ______________ Date: ______

Do I need a W-9 and a 1099 for my subs?

Get the W-9 before you pay. It gives you the sub's legal name, tax classification and tax ID, and it tells you whether a 1099 is likely. If you owe one depends on what you paid that sub in the year and how they're taxed. The details and the current threshold are in the 1099 for subcontractors guide. Don't carry a number from memory. It changed.

Paying by card or a payment app can move the reporting to someone else. That's in the guide too. Keep your own record either way.

What insurance should a sub carry?

At minimum general liability, and workers' comp if they have anyone working for them. Ask for the certificate of insurance and read it. Look at the policy dates, the coverage limits, and if you're listed as additional insured. A waiver of subrogation is worth a conversation with your own insurance agent.

Put the expiry date in your calendar. A COI that was good in March can be dead in September. A sub who got hurt on your job with no active policy is your problem.

Should I pay a sub only when the homeowner pays me?

It's a term you will see called pay-when-paid or pay-if-paid. Courts and state laws can treat the two differently, and your state may limit them. So the decision is yours and your attorney's. Here is how the choices look in practice.

Payment termWhat it saysWhat it means day to day
Pay on completionSub is paid after the work is done and inspectedSimple. You carry the cash gap
Pay-when-paidSub is paid after you're paid by the clientProtects your cash flow. Subs push back on it
Pay on scheduleSub is paid on set dates or stages, regardless of the clientSubs like it. You carry the risk

Whatever you choose, write it in one sentence on the agreement. "Payment is due 7 days after the sub's invoice and my inspection of the work." Don't leave it vague.

What about lien waivers?

Ask for a lien waiver every time you pay a sub, signed when they get paid. The forms and rules differ by state, and some states publish their own. Nailed doesn't do lien waivers, so keep a folder of them yourself. A file per job with the sub's invoice, your check or transfer, and the signed waiver is enough. If you plan to hold retainage from a sub, see progress payments and retainage.

How do I handle changes and finishing?

Same rule as with the homeowner: nothing extra gets done without a number agreed first. Write "no extra work without a signed change, priced before work starts" on the agreement and use it. For ending the agreement, name what counts as default and give a notice period to fix it. If a sub bails, the notice and the right to bring in someone else are what keep you from eating the whole cost.

How does Nailed fit in?

Nailed doesn't write subcontracts. Where it helps is the cost side. When you pay a sub, text it: "paid the guys 1,000 on Klein." Nailed files that as labor on the Klein job, so your profit on that job counts it. Send a photo of a sub's invoice or a supplier receipt and it reads and files it to the right job too. Quotes and anything money-related wait for your tap.

Nailed on WhatsApp
  1. You: paid the guys 1,000 on Klein
  2. Nailed: Logged $1,000 labor on Klein. Want the profit so far?
  3. You: yes
  4. Nailed: Klein is at 22% margin so far.

See the AI office manager for contractors, track expenses per job and how Nailed works. If you're pricing sub labor into a bid, the labor rate calculator helps. Terms like COI and W-9 are in the contractor glossary. When a sub's work comes up at closeout, use the punch list template.

Frequently asked questions

Do I need a written contract with a subcontractor?

It's the safer habit. A handshake leaves price, schedule and who fixes what up to memory. Even a one-page signed scope and price beats nothing. For anything large, or if you're unsure what your state requires, have a local attorney write or review your standard agreement.

Who pays for materials and tools?

Whoever the agreement says. Write it down either way. Most subs bring their own tools. For materials, say whether the sub supplies them in the price or you buy them, and who handles delivery, storage and waste.

What insurance should a sub carry?

At least general liability, and workers' comp if they have employees. Ask for a certificate of insurance (COI) that names you as additional insured, and note the expiry date. Required limits and rules differ by state and by your own policy, so check both.

What if the sub doesn't finish the job?

Your agreement should say what counts as default, how many days you give them to fix it, and what happens to payment for unfinished work. Without those words, you're negotiating in the middle of a mess. Have an attorney look at that clause.

Can I charge a sub for delays?

Only if the agreement says so, with clear terms about what a delay is and how much. A vague clause rarely holds up. Whether and how such clauses are enforced depends on your state, so ask a local attorney before you rely on one.