Punch List Template for Residential Jobs (Filled Example)

By Roy, Founder of Nailed. Published . 6 min read.

Nailed handles the office paperwork from your texts. Try it free

A punch list is the written list of small items left to finish or fix before the client accepts the job. The useful version is signed by both of you, and it is what the final payment hangs on. A filled residential list is below, and it is tied to the last invoice.

What goes on a residential punch list?

Anything small, visible or functional that is not finished or not right: touch-up paint, a sticking door, a missing outlet cover, a caulk gap, a cracked tile, a drawer that rubs. Big scope you forgot is not a punch item. That is a change order.

Group the list by room, and write each item so someone else could fix it without calling you. "Bath: caulk gap at tub, east wall, 18 in." beats "bath caulk".

Punch list template with a filled example

This is a made-up list for the same $48,000 bath and hall remodel used in the retainage guide. Copy the whole block. Replace the examples.

Punch list: filled example

PUNCH LIST Job: Klein bath and hall remodel, 112 Maple St Contractor: [Company] Owner: [Name] Walk-through date: [date] Contract price: $48,000

No. | Room | Item | Who | Fix by | Status | Owner initials 1 | Bath | Caulk gap at tub, east wall, about 18 in. | GC | [date] | Open | ___ 2 | Bath | Touch up paint above vanity mirror | GC | [date] | Open | ___ 3 | Bath | Replace cracked floor tile by door (1 tile) | Tile sub | [date] | Open | ___ 4 | Bath | Adjust shower door, rubs at bottom | GC | [date] | Open | ___ 5 | Bath | Exhaust fan rattles on high | Electrician | [date] | Open | ___ 6 | Bath | Missing outlet cover, left of sink | GC | [date] | Open | ___ 7 | Hall | Door to linen closet sticks at top | GC | [date] | Open | ___ 8 | Hall | Fill nail pops in ceiling, repaint patch | Drywall sub | [date] | Open | ___ 9 | Hall | Baseboard gap at corner by bath door | GC | [date] | Open | ___ 10 | Vanity | Drawer 2 rubs on rail | GC | [date] | Open | ___ 11 | Whole job | Remove protection film, clean tile and glass | GC | [date] | Open | ___ 12 | Whole job | Put attic access panel back, hall ceiling | GC | [date] | Open | ___

Items 1 to 10 fixed and initialed on [date]. Items 11 and 12 open at sign-off. Open items and the dollar amount held for each: Item 8: $200 Item 10: $150 Total held: $350

Final payment tie-in Retainage and final payment: $1,620 Less amount held for open items: $350 Released at sign-off: $1,270 Released when items 8 and 10 are done and initialed: $350

Owner signature: __________ Date: ______ Contractor signature: __________ Date: ______

Keep the arithmetic honest. $1,620 minus $350 is $1,270 released now, and $350 when the last two items are initialed. The amounts per item are an example, not a rule. Pick numbers that match what it would cost you to fix each one.

Who makes the punch list, you or the homeowner?

Both of you, on one document. Walk it yourself the day before and fix what you can. Then walk it with the homeowner, with the list in hand, and let them add anything they see. One person writes. Both initial.

Do not accept a list that arrives by text in pieces over a week. Decide the walk-through date in advance and close the list that day. Anything new after sign-off goes on a warranty page.

How does a punch list tie to final payment and retainage?

It becomes the trigger. The contract says final payment, and any retainage, is due when the punch list is signed and any required inspection has passed. No signature means no clock.

That is why the last rows of the sheet above matter. Each one has a job:

  1. Name the amount due at sign-off.
  2. Name the small amount held for any open item, and what releases it.
  3. Put both signatures on it.

The release language, and how a 5 percent holdback works through a job, is in the progress payments and retainage guide. Some states also set a reserve period by law. Texas, for example, tells owners to reserve 10 percent during the work and for 30 days after completion. Check your own state before you set a date.

If your final payment comes with a lien waiver, sign-off is the time to swap it for the money. Which form you use depends on your state.

How much can a homeowner hold for open punch items?

Whatever your contract allows. Here are the ways it usually gets written:

Contract optionHow it worksWatch out for
Agreed amount per itemEach open item has a dollar figure on the listNeeds both people to agree at the walk-through
Fixed holdbackA set amount, like retainage, stays until the list is doneNeeds a release date or it drags
No clauseNothing saysClient may hold the full balance, and you are in a dispute

Whichever you choose, write it in the agreement and have an attorney read it. This page won't hand you a standard figure, because there isn't one.

How long do you have to finish the punch list?

As long as the contract says. If it says nothing, you have no clock, and neither does the client. Put a window in. Fourteen days is the example used in the retainage guide, but pick what fits the job. Extra time for special-order parts belongs on the list, with the date next to it.

Should you use a punch list for every job?

For anything with a final payment worth chasing, yes. On a two-hour repair, no. A walk-through on a bath or kitchen takes 20 minutes and saves you a week of texting about a drawer.

Where Nailed fits

Nailed does not run punch lists. It is not a punch-list app. What it does is keep the money side of the closeout straight. Put the release as its own installment on the quote, and Nailed emails the client a reminder in your name when it is due. When the payment lands, you tell it and the reminders stop.

Nailed on WhatsApp
  1. You: Klein punch list signed today. Two items open, 350 held. Send her the balance.
  2. Nailed: Drafted an email to Mrs. Klein with what she has paid to date and the balance due, with a read-only link. Tap Send to go out.
  3. You: Klein paid 1,270.
  4. Nailed: Logged $1,270 on Klein. Reminders for that payment are stopped.

You can see the other pieces in how it works and the AI office manager for contractors. If you want the whole payment plan on one page, use the contractor payment schedule template. For small changes found at the walk-through that are not punch items, use the change order template. The one-page form that the signed list rides behind is the final walkthrough sign-off template. Texts for the final ask and the thank-you are in payment request messages and payment received messages, and the contractor glossary covers the rest of the closeout words.

Frequently asked questions

Who makes the punch list, the contractor or the homeowner?

Both, in a good job. You walk it first and list what you know is left. Then the homeowner walks it and adds what they see. Agree on one list, with both initials, so there is a single version when the final payment comes due.

Can the homeowner withhold payment until the punch list is done?

Only what your contract allows, plus whatever your state's law says. Some contracts name a retainage amount or a value per open item. If yours says nothing, expect an argument. Write the hold into the contract before the job starts and ask a local attorney.

Is a punch list the same as a snag list?

Same idea, different word. Snag list is the term in the UK and some other countries. In the US you will hear punch list, closeout list or walk-through list. Whatever you call it, it is the list of small items left before the job is accepted.

What is the difference between a punch list and warranty items?

A punch list is what is unfinished or wrong when you hand the job over. A warranty item is something that fails or turns out defective after the client has accepted the work. Keep them on separate pages, so a new problem in month four is not argued as an old punch item.