Contractor Payment Schedule Template With 3 Filled Examples
Nailed sends the payment reminders so you don't have to. Try it free
Tie every payment to something the client can see on site. Keep real money for the last one. Stay inside your state's deposit rules. Then put it all in the contract before you start. Below: a template to copy, and three worked examples that add up to the dollar.
Download it: Google Sheets / Excel (.csv). Change the contract total and the amounts and the sum check update.
What is a contractor payment schedule?
It's the list of payments the client agrees to make, how much each one is, and what has to be done first. The progress payments are the draws. It goes in the signed contract so nobody's arguing about "when" or "how much" halfway through.
No schedule means "pay at the end." Fine for a $900 repair. On anything bigger you're floating the client's project out of your own account, and when a dispute comes, it comes right when you're owed the most.
What does a payment schedule template look like?
Paste this into a quote, a contract or a text, then fill the brackets. If you can't photograph the milestone, it's too vague. Every payment needs an amount, a trigger and a due date, and the amounts must add up to the contract total. The sheet download does that check for you.
PAYMENT SCHEDULE Job: [job name and address] Contract total: $[total]
- Deposit, due at signing: $[amount]
- Final payment, due on completion and punch list sign-off: $[amount]
Total of payments 1 to 5: $[must equal contract total]
Terms:
- Each payment is due within [3] days after its milestone is complete.
- Changes to the scope are priced in a written change order and added to the next payment.
- Work may pause if a payment is more than [5] days late, after written notice.
- Late fee, if any: [state it here and only if your contract allows it].
Add the payments up before you send it. A schedule that's $50 off starts the exact argument you were trying to avoid.
How should I split a $15,000 job?
Four payments is plenty. Take a small deposit, a payment when the messy work is done, another when the main install is in, and hold a decent chunk for completion. Think bathroom refresh or a small deck. The shares below are an example, not a rule.
| # | Milestone | Amount | Share |
|---|---|---|---|
| 1 | Deposit at signing | $1,500 | 10% |
| 2 | Demo done, rough-in complete | $4,500 | 30% |
| 3 | Tile and fixtures installed | $6,000 | 40% |
| 4 | Completion and punch list sign-off | $3,000 | 20% |
| Total | $15,000 | 100% |
1,500 + 4,500 + 6,000 + 3,000 = 15,000.
How should I split a $60,000 job?
Add a payment when the big materials land, because cabinets and counters tie up real money you'd otherwise carry yourself. Six payments is typical on a job this size. Think full kitchen remodel. Check your state's deposit cap before you copy the first row.
| # | Milestone | Amount | Share |
|---|---|---|---|
| 1 | Deposit at signing | $6,000 | 10% |
| 2 | Cabinets delivered to site | $12,000 | 20% |
| 3 | Demo and rough plumbing and electrical pass inspection | $9,000 | 15% |
| 4 | Cabinets installed | $12,000 | 20% |
| 5 | Counters and backsplash installed | $9,000 | 15% |
| 6 | Completion and punch list sign-off | $12,000 | 20% |
| Total | $60,000 | 100% |
6,000 + 12,000 + 9,000 + 12,000 + 9,000 + 12,000 = 60,000.
How should I split a $190,000 job?
Now you're on draws tied to construction stages, usually the ones an inspector signs off. There are more payments, each one small next to the whole, and retainage might come up. Think one-story addition, and have your attorney read the contract.
| # | Milestone | Amount | Share |
|---|---|---|---|
| 1 | Deposit at signing | $19,000 | 10% |
| 2 | Foundation poured and inspected | $28,500 | 15% |
| 3 | Framing and roof dried in | $38,000 | 20% |
| 4 | Rough mechanical, electrical and plumbing pass | $28,500 | 15% |
| 5 | Insulation and drywall complete | $28,500 | 15% |
| 6 | Cabinets, trim and flooring installed | $28,500 | 15% |
| 7 | Completion, final inspection and punch list | $19,000 | 10% |
| Total | $190,000 | 100% |
19,000 + 28,500 + 38,000 + 28,500 + 28,500 + 28,500 + 19,000 = 190,000.
What if the client wants retainage?
The client holds back a percentage of each progress payment until the end. Common on commercial work, sometimes asked for on big residential jobs. It's negotiable. It's not a default.
Say the client holds 5% of draws 2 through 6. Those draws total $152,000, so retainage is $7,600. Your final payment becomes $19,000 + $7,600 = $26,600, released at sign-off. You're carrying $7,600 of cost until the very end. If you agree to retainage, price it in or cap it.
How big should the deposit be?
Small enough to defend. Ten percent is a common starting point, and some states cap it by law. It should cover real early costs, like permits and ordering, not fund the whole job. Check your state before you put a number in the contract.
Why not take more money up front?
Because it backfires. In some states it's illegal. And clients notice: you've been paid 60% and you're 20% done, so you have no pull and not much credibility. The closer your payments track the work, the easier every conversation gets.
It bites hardest when something goes wrong. A sub no-shows, a delivery slips, and you're already overpaid. Now the client has every reason to stop paying. Stay a step behind the work, not ahead of it.
What rules of thumb make a schedule work?
Keep it simple and visible. If the client can check each milestone from the driveway, they pay without a fight. These are rules of thumb from how small shops run, not legal standards, so adjust them to your state and your contract.
- Milestones, not dates. "Cabinets installed" beats "June 15." Weather and deliveries slip.
- Keep 10 to 20 percent for the end. A rule of thumb, not a legal standard. It's what gets the punch list done.
- Match big material buys. If you're fronting $12,000 of cabinets, a payment should land when they show up.
- Ask the same day. Wait a week to ask and you wait a week to get paid. Put clear terms in the contract, like due in 3 days.
- Price changes separately. Anything outside scope goes in a written change order. Use the change order template, and see how to get change orders signed.
- Add the numbers up. Every time.
For what to say when a draw runs late, see how to get clients to pay on time.
How can I run my schedule from my phone?
Nailed sets up the schedule on the signed quote, with each payment and its due date. When one comes due it emails the client a reminder in your name, and logging the payment stops them. You see each morning's reminders at 8 and can hold any of them. Quotes and any change to an amount always wait for your tap.
- You: Cabinets are in at the Brooks kitchen.
- Nailed: That's draw 4 on the Brooks schedule, $12,000. I'll email them a reminder in your name when it's due. You'll see it at 8 that morning and can hold it. If it goes late, I'll ask you what's next.
- You: Brooks paid draw 4, check 2208
- Nailed: Logged $12,000.00 from Brooks, check 2208. Reminders for draw 4 are off. Draw 5 is next, counters and backsplash, $9,000.00.
The amounts come from the schedule you approved, not from the AI's guess. Nailed is an AI office manager for contractors you run by text. See how it works or pricing.
Getting paid is half of it. What the job actually earned after the draws clear is the other half, and the profit margin guide works through one.
Each draw needs an invoice, and the construction invoice template shows what to put on it.
Frequently asked questions
What is a draw schedule?
A draw schedule is the list of payments a client makes as the job moves along, each one tied to a finished milestone. Contractors call each payment a draw. It beats one big bill at the end, and it keeps you from running dry mid-job.
How many payments should a remodel have?
Three or four on a small job. Five or six on a mid-size remodel. Add a payment only when something real and visible happens on site. Every extra payment is one more thing to ask for and chase, so don't add one just to smooth out the numbers.
Should the last payment be bigger than the rest?
Yes. Keep a real amount for completion, 10 to 20 percent on a mid-size job. A big last payment gives the client a reason to sign off the punch list, and it gives you a reason to actually finish it.
Do I need a lien waiver with each payment?
Often, yes. Some states have set forms and rules. A waiver says you were paid for work through a certain date, and clients and lenders often ask for one with each draw. It varies by state, so ask a local construction attorney before you lean on one.