How to Get Change Orders Signed Before the Work Starts

By Roy, Founder of Nailed. Published . 7 min read.

Nailed turns "they want to add a window" into a change order the client signs on their phone. Try it free

Get it signed before the work starts. Not when you invoice, not at the walkthrough. No signature, no work. The hard part is saying that to a friendly homeowner standing in her own kitchen, so here are the words.

Why do change orders get signed late, or not at all?

Because it feels rude to stop for paperwork when the client's standing right there and the fix takes ten minutes. She hears "extra" as a favor. You hear it as money. Without a signed number, both memories drift. A better contract won't fix that. A habit will.

The cost is real. See what one unbilled change did to a $48,000 kitchen's net profit.

What is the "no signature, no work" rule?

You don't start anything outside the contract until the client approves the price and schedule in writing. No big speech. You tell every client on day one and put it in the contract, so on site you're only reminding them.

Put this in your original contract:

Contract clause (adapt with your attorney)

Changes to the scope of work, price or schedule must be agreed in writing by both parties before the changed work begins. Written approval may be given by signature on a change order or by electronic signature. The contractor is not required to start changed work until the change order is approved.

What do I say on site when the client asks for something extra?

Say yes to the idea. Slow down the start. You're not refusing, you're pricing. The client hears a yes, and you get the minutes you need to work out the real cost and the added days before anybody picks up a tool.

On-site script

"Sure, we can do that. Give me a minute to figure out what it adds. I'll text you the number and the days it adds in the next hour. You say yes, we start. I do it this way on every job so nobody's surprised at the end."

Then leave it alone. Don't start "while you wait for the text." That's the mistake. Once you've started, the price is an argument. Before you start, it's a quote.

What text do I send?

One message the client can answer with one word. The price, the days and the new total, all in the text. That's fine for small changes. Anything over your threshold gets a full signed change order, like the one in the free change order template.

Text to send

Hi [name], here's the change we talked about: [what, where, which product]. Cost: $[amount]. Adds [x] working day(s). New contract total: $[amount]. Reply YES and I'll start. If you want to skip it, reply NO and we carry on as planned. Good until [date].

They reply "yes"? Screenshot the thread into the job file. They reply "ok sure but can you do it cheaper?" Then you don't have an approval. Reprice and ask again.

When should the change order be sent and signed?

Send it the same day. Get it signed before you order material, book a sub or move a crew. The right moment depends on what triggered the change, and the table below shows when to send and when it has to be signed for each case:

SituationSendSigned before
Client asks on siteWithin the hourAnything starts
You find a hidden problem (rot, wiring)Same day, with photosYou close it back up
Inspector requires a fixSame day, cite the itemThe fix starts
Material unavailable, substitute neededWhen you learn itYou order the substitute
Emergency (active leak, safety)Text while you make it safeAny work past making it safe

Emergency? Make it safe first, send the paper right after, and write down what you did and when.

How do I price a change on the spot?

Use the same method every time, so you're not inventing numbers while somebody watches. Hours times your rate, plus material, plus your usual markup, plus the days it adds to the schedule. Say it once, write it down, and keep the math simple enough to check in the truck.

An example, nothing more: a homeowner wants two extra outlets in the kitchen.

  • Labor: 3 hrs x $85 = $255.00
  • Materials: $60.00
  • Subtotal: $315.00
  • Markup (15%): $47.25
  • Change total: $362.25

On a $22,000 contract, the new total is $22,362.25. That's a calculator in the truck and under a minute. If the change touches several trades or needs a sub's quote, say "I'll have the number tonight." Don't guess. A bad price you said out loud is hard to walk back.

Every price needs a markup line you can explain and a schedule number. The change order template has all the fields. If the change moves the money, update your payment schedule too.

What do I say when they say "just do it, we'll sort it out later"?

Don't argue. Agree, then turn "later" into a number. This is where most unpaid extras begin, because "later" never gets a price and both of you remember the deal differently. Have the line ready before you need it, and say it the same way every time.

Script for 'just do it, we'll sort it out later'

"Happy to. It'll take me two minutes to write it up so we both know what we agreed. I'm sending you the price now. A yes by text and I'm on it. I do this on every job, it protects you as much as me."

Still pushing? Fall back to this:

Fallback if they keep pushing

"I don't start extras without a number on paper. Not because I don't trust you. Because six weeks from now we'll both remember it differently. Reply yes to the text and I'll start right away."

Then go on with the contracted work and leave the extra alone until the text comes back. Most clients answer within the hour. The ones who don't were going to dispute it anyway. And when the extra is signed, bill it on time: here's how to get clients to pay on time.

What if the client says no to the price?

Good. You found out before you did the work. Offer a cheaper version, drop it, or park it as a separate job for later. A "no" on paper costs you nothing. A "no" after the work is done costs you the work.

Are electronic signatures valid on change orders?

Generally, yes. The federal ESIGN Act says a signature can't be denied legal effect solely because it's electronic (15 U.S.C. 7001(a)), and most states have a matching law. A tap on a phone counts if the client meant to sign. Keep a record of who signed and when. The change order template has the details.

How do I do this by texting Nailed?

Today Nailed turns a voice note into a quote, sends it out for e-signature (the client taps a link, no login) and files the signed copy under the job. No quote goes out until you tap Send. A mid-job change goes out as a revised quote the client e-signs. Change orders as their own feature are coming soon.

Nailed on WhatsApp
  1. You: Hendry kitchen, she wants two more outlets by the island. 3 hrs, 60 in material
  2. Nailed: Labor 3 hrs at $85 is $255.00. Materials $60.00. Subtotal $315.00. Your 15% markup is $47.25. Change total $362.25, new contract total $22,362.25. Send her a revised quote to sign?
  3. You: yes
  4. Nailed: Sent. She signs from a link, no login. I'll tell you here in the chat the second it's signed. Change orders as their own document are coming soon, so this goes out as a revised quote.
  5. Nailed: Signed. The revised quote is in the Hendry job file. You're good to order the outlets.

You never start without the yes. More on how it works, the AI office manager for contractors and pricing.

Whether a typed or drawn signature holds up is covered in e-signatures on construction contracts.

Frequently asked questions

What if the client refuses to pay for a change they asked for?

Point to the signed paper or the text thread. Nothing signed? Offer to drop that item and finish the contracted scope, or sign it now at the quoted price. Don't hold the whole job hostage until you've read your contract and your state's rules.

Is a verbal change order enforceable?

Sometimes. It's hard to prove, though, and some states, California among them, require written changes on home improvement contracts. Even where it's allowed, you're arguing about who said what. A one-line text the client answers with a yes beats anybody's memory.

How fast should a change order go out?

Same day, ideally within the hour while the conversation is fresh. Send it before you order material or move a crew. Put a short expiry on it, like 7 days, so stale pricing doesn't hang around when material costs move.

Can I charge for the time spent pricing a change?

Only if your contract says so. Most small GCs eat the quick ones and charge for bigger design or engineering work, which is where the real hours go. If a change needs real estimating hours, put that in the contract up front, with the rate.