Progress Payments and Retainage on a Residential Job
Nailed sends the payment reminders so you don't have to. Try it free
Retainage is a slice of each progress payment that the client holds back until the work is finished and accepted. On a house the percentage is whatever your contract says, and it is the last money you collect. If you agree to it, make the release a signed event, not a feeling.
What is retainage in construction?
Retainage is a percentage held back from each payment and released at the end, once the work is complete and accepted. It exists to give the client a say: if the paint is wrong or the punch list drags, they still have money in their hand. The word is also spelled "retention" or just "holdback."
Think of it as a second, smaller deposit that runs the other direction. The client's deposit protects you at the start. Retainage protects them at the finish.
Who holds retainage on a house, and why?
On a large commercial job, the owner holds it from the general, and the general holds it from the subs. On a house, it is usually the homeowner or their lender holding it from you. Some states also have laws that tell an owner to reserve a share of the contract during the work.
Texas is one example. Its property code says that during the work, and for 30 days after the work under the contract is completed, the owner shall reserve 10 percent of the contract price (or 10 percent of the value of the work done). That is one state's rule, written for mechanic's lien purposes. It is not a national standard, and this page can't tell you what applies where you work.
How much retainage is normal on a residential remodel?
There is no residential standard. You will see numbers like 5 or 10 percent quoted, but they come from contracts and habit, not from a rule that sets it for you. Your contract sets it. Here are three ways it can look on the example job below.
| Retainage | What it means on a $48,000 job | Who usually asks |
|---|---|---|
| None | $0 held | Small jobs, repeat clients, deposits only |
| 5% on draws | $1,620 held (draws 2 to 4 in the example below) | A careful homeowner or a lender |
| 10% of the contract | $4,800 held | An owner reserving funds the way some state laws describe |
If a client asks for 10 percent and you can get 5, try 5. If they will not move, cap it and put a date on it. More on that below.
What is a progress payment, and is it the same as a draw?
A progress payment is a partial payment while the work is going on. A draw is the same thing on most houses. The only difference is habit: "draw" usually means payments tied to stages, and "progress payment" is what the paperwork calls it.
What matters is what triggers each one. Tie it to a stage the client can see or an inspector can sign. If you need a starting schedule, the contractor payment schedule template has one for small jobs and one for bigger ones. And how much you can ask for up front is covered in how much deposit a contractor can ask for.
What does retainage cost a small GC? A worked example
Take a $48,000 bathroom and hall remodel. Deposit is 10 percent. The rest goes out in four equal draws. The client holds 5 percent of draws 2, 3 and 4, and releases it at sign-off. These are made-up numbers to show the arithmetic.
- Deposit: 10% of $48,000 = $4,800
- Left to bill: $48,000 - $4,800 = $43,200
- Four draws of $43,200 / 4 = $10,800 each
- Retainage on draws 2 to 4: 5% of $10,800 = $540 each time
| Invoice | Billed | Held back | Cash you receive |
|---|---|---|---|
| Deposit at signing | $4,800 | $0 | $4,800 |
| Draw 1: demo and rough-in passed | $10,800 | $0 | $10,800 |
| Draw 2: tile set | $10,800 | $540 | $10,260 |
| Draw 3: fixtures and cabinets | $10,800 | $540 | $10,260 |
| Draw 4: substantially done | $10,800 | $540 | $10,260 |
| Retainage release (signed punch list) | $1,620 | $0 | $1,620 |
| Total | $48,000 | $48,000 |
Look at where you stand when draw 3 is paid. You have billed $37,200 ($4,800 + three draws of $10,800). You have been paid $36,120. So $1,080 of finished work is sitting in the client's account. After draw 4 it is $1,620, and it stays there through the punch list.
What is the carrying cost?
Smaller than people think. Say you finance that money at 12 percent a year and wait 90 days.
- 5% case: $1,620 x 12% x 90 / 365 = about $48, or 0.1% of the contract.
- 10% case: $4,800 x 12% x 90 / 365 = about $142, or 0.3% of the contract.
So the interest is a rounding error. The real cost is that the last $1,620 depends on someone else's decision, on their schedule. That is the part you price in your head.
Agree, cap, or price it in?
You have three honest moves. Pick one per job and say which on the quote.
| Move | When | What you do | Cost to you |
|---|---|---|---|
| Agree | Good client, small percentage, clear release | Accept 5% with a written trigger | About 0.1% of price in carrying cost on the example |
| Cap | Client wants 10% or "until we are happy" | Cap at 5%, release within 14 days of sign-off | Same, with an end date |
| Price it in | You will take any rate but want to be covered | Add the carrying cost to the price, about 0.3% on the 10% case | Client sees a slightly higher number |
Pricing it in is the wrong fight. The dollars are tiny. What you need is the release date. If you want to check what a small bump does to your margin, the markup and margin calculator does it in a minute.
When does a contractor get retainage released?
When the release trigger in your contract happens. If the contract is silent, you are guessing. A state law may also set a date, like the 30 days in the Texas example, so read the rule for your state before you promise a number of days.
The trigger should be an event with a signature on it, not a mood. Here is a sentence you can adapt and ask your attorney to look at:
Retainage of [5]% withheld from progress payments will be released and is due within [14] days after (1) Owner and Contractor sign the final punch list, (2) any required final inspection has passed, and (3) Contractor delivers [final lien waiver / release if required in this state]. Items on the signed punch list that remain open will be completed within [30] days, and a dollar amount for each open item, agreed on the list, may be withheld until it is done.
That last sentence matters. If two small items are open, the client holds only what those items are worth, not the whole $1,620. A filled-in list you can copy is in the punch list template.
If a lien waiver is part of your final payment, rules and forms differ by state. Ask your attorney which one to use.
What if the homeowner will not release retainage after the punch list?
Start with the paper. Did you both sign the list? Did the clock start? If yes, send one written request that quotes the clause and the date, and attach the signed list.
Is something genuinely not done? Finish it, get it signed, then ask again. If the client is simply sitting on it, what to do when a homeowner won't pay is the next read. A demand through a lawyer is a state-by-state question, and this page won't guess at it.
How do you bill progress payments without an argument?
Tie each one to a visible stage, name it on the quote, and send it the same day the stage is done. "Tile set" is hard to argue with. "About 60 percent" is a coin flip.
Put retainage in its own row on the payment schedule. Then it gets an invoice, a due date and a reminder like every other payment. Otherwise it quietly falls off the list, and it is the payment you are most likely to forget.
Here is how that looks when you text Nailed.
- You: Quote for Klein, bath and hall remodel, 48,000. 10% down, four draws of 10,800, 5% held on draws 2 to 4, release 1,620 when the punch list is signed.
- Nailed: Draft ready. $48,000. Deposit $4,800 at signing, draws 1 to 4, and a last payment of $1,620 on the signed punch list. Tap Send when the schedule looks right.
- You: Klein paid draw 2. 10,260 came in.
- Nailed: Logged $10,260 on Klein for draw 2. The reminders for that payment are stopped. Next is draw 3, $10,260 after the hold.
Nailed tracks the payments and emails the client reminders in your name when a payment is due. Logging the payment stops them. It does not move the money; the client pays you however you set up. The quote and the schedule wait for your tap. To see how it works, check how it works, or read how to get clients to pay on time and the payment reminder messages. For the texts that go with each draw, see payment request messages and payment received messages. Unfamiliar word? The contractor glossary has it.
For a full picture of what an office manager does for a GC, see the AI office manager for contractors.
When a draw comes due, send it with a proper invoice. The construction invoice template has the fields to include.
Frequently asked questions
Can a homeowner hold back retainage from a contractor?
Only if the contract says so, or a law in your state requires an owner to reserve funds. Some states do. If your contract is silent and the homeowner holds money back anyway, you have a dispute, not a retainage clause. Put the percentage and release date in writing before you start.
What is the difference between a progress payment and a draw?
Mostly nothing on a house. Both mean a partial payment as the job moves. Draw is the word people use when the payments follow stages, like framing done or cabinets set. Progress payment is the paperwork term. Either way, you bill a slice of the contract, not the whole thing.
How do I bill percent complete without an argument?
Tie each draw to something the client can see or an inspector can sign, not a percentage you guess. Framing passed, drywall hung, cabinets set. A stage they can walk through is hard to dispute. A figure like 'we are about 60 percent done' invites a negotiation.
Is retainage legal in my state?
It depends on the state, the type of job and who is holding the money. Some states cap it, some require owners to reserve it, some restrict it on certain projects. This guide can't tell you which applies to you. Ask a local construction attorney or your state contractor board.