Fixed Price vs Time and Materials vs Cost Plus for Remodels

By Roy, Founder of Nailed. Published . 7 min read.

Nailed files every receipt to the right job and tells you what each one is making. Try it free

Three common ways to price a remodel. Fixed price is one number, and you eat the surprises. Time and materials means you bill hours and receipts as you go. Cost plus means you bill your actual costs plus a fee. Fixed price fits a clear scope. The other two fit work where nobody knows what's behind the wall.

What is the difference between fixed price, time and materials, and cost plus?

Fixed price is one agreed total for a defined scope. Time and materials bills labor by the hour at a set rate, and materials at cost or with a markup. Cost plus bills your actual costs, labor included, plus a fee, either a percentage or a flat amount.

The real difference is who holds the risk.

  • Fixed price: you hold it. Come in under and you keep the gain. Run over and you eat it.
  • Time and materials: the homeowner holds most of it. You get paid for the hours you work.
  • Cost plus: the homeowner holds it too, but you show your actual costs, so trust and records matter more.

What does the same job look like priced three ways?

One kitchen remodel, with example numbers. They aren't market data, and your costs will differ.

Say you estimate your cost at $20,000. Your real cost ends up at $21,000, which is 5% over:

  • Materials: $9,200
  • Your crew's labor: 160 hours at $45 loaded cost, so $7,200
  • Subs (electric and plumbing): $4,600

That's $21,000 of actual cost.

Fixed price. You bid cost plus 25% markup on your $20,000 estimate: $25,000. The job cost $21,000. Profit is $4,000. Margin on price is 16.0%. The overrun cost you $1,000 of the $5,000 you hoped for.

Time and materials. You bill labor at $75 an hour, and materials and subs at cost plus 15%.

  • Labor: 160 hours x $75 = $12,000
  • Materials: $9,200 x 1.15 = $10,580
  • Subs: $4,600 x 1.15 = $5,290
  • Total bill: $27,870

Profit is $6,870 on a $21,000 cost. Margin is 24.7%. It's higher because the labor rate covers more than the $45 you pay. That $30 an hour has to cover overhead too, so don't read this as pure profit.

Cost plus. You bill $21,000 of actual cost plus a 20% fee: $25,200. Profit is the $4,200 fee. Margin is 16.7%.

Fixed priceTime and materialsCost plus 20%
Homeowner pays$25,000$27,870$25,200
Your cost$21,000$21,000$21,000
Your profit$4,000$6,870$4,200
Margin on price16.0%24.7%16.7%

Look at what happens when the job goes wrong. Say the crew needs 200 hours instead of 160 because the floor was rotten. Actual cost becomes $22,800.

  • Fixed price: the price stays $25,000. Profit drops to $2,200. Margin 8.8%.
  • Time and materials: labor bills 200 x $75 = $15,000. Total $30,870. Profit $8,070. Margin 26.1%.
  • Cost plus 20%: $22,800 x 1.20 = $27,360. Profit $4,560. Margin 16.7%.

Same job, same surprise. Fixed price lost almost half its profit. Cost plus held its margin. Time and materials went up.

That's why homeowners are wary of the second and third types. Their bill grew by $2,160 to $3,000 for the same kitchen. A written cap is the fair fix, covered below.

When should a GC use a fixed price contract?

Use fixed price when the scope is clear on paper and you've seen the space: new cabinets in an existing layout, a bathroom gut where the plumbing stays put, a deck. The homeowner gets one number. You get an easy sale and a simple payment schedule.

It breaks down when you can't see what you're pricing. Old houses, water damage, anything behind drywall. Bid those at a fixed price and you either pad the number until it loses the job, or you gamble.

It also needs a tight scope, because every "while you're here" request becomes a change order. For that process, read how to get change orders signed.

When is time and materials or cost plus the better call?

Use time and materials for small, open-ended work: repairs, punch lists, a day of "figure out what's wrong." Use cost plus for bigger jobs where the scope will move and the homeowner values flexibility, or where the project is mostly unknown until demo.

Both need three things:

  1. A written rate sheet or fee percentage before you start.
  2. A cap or an estimate range, so the homeowner isn't signing a blank check.
  3. Receipts and hours on file for every job, ready to show.

Skip the third and you'll be arguing. Keep it and the bill defends itself.

Should a small GC mix them?

Often, yes. A common split on old houses: fixed price for the known scope, plus a time and materials allowance for whatever turns up after demo, with a cap and a written approval step. The homeowner gets a firm number for most of the job, and you aren't gambling on the rest.

Whichever way you go, write down what happens to unknowns before the first day. A one-line "hidden conditions billed at cost plus 15%, with your OK first" in the contract saves a hard conversation later.

How do I pick one?

Your situationBest fitWhy
Clear scope, you've seen the spaceFixed priceOne number, easy sale, you keep the gain
Old house, unknown conditionsCost plus with a cap, or fixed plus allowanceRisk shared, no padding
Small repair or punch listTime and materialsQuick to quote, paid for the hours
Homeowner insists on a firm totalFixed price with written exclusionsScope defines the price
Homeowner wants to watch every costCost plusOpen books, a fee you both agreed on
Your records are weakFixed priceThe other two need proof
Your estimating is weakCost plus or time and materialsDon't carry the guess

The last row is blunt, but true. If you keep losing money on fixed bids, the fix may be better costing, not a new contract type. How to price a remodeling job covers that.

How do margins compare?

In the example above, fixed price made 16.0% and cost plus 16.7%. Neither number means much until you compare it to your overhead. If your overhead is 20% of revenue, a 16% margin loses money after the office costs. Work out your real number first with the general contractor profit margin guide.

One trap: a percentage fee on cost plus pays you more when costs rise. Homeowners know it, and some will push for a flat fee. A flat $4,200 on the same job works too. You just don't earn more on a bigger overrun, which is fair.

How should I set up payments for each type?

Fixed price pairs with a deposit and milestone payments tied to stages. Time and materials and cost plus usually bill every week or two from actual costs. The contractor payment schedule template has fixed-price examples at $15k, $60k and $190k.

Whatever you pick, check whether your state caps deposits on home improvement work. Some do.

How does Nailed fit in?

On cost plus and time and materials, the whole game is records. Nailed reads receipts and supplier invoices you send as a photo or PDF and files them to the right job. A text like "paid the guys 1,000 on Klein" works too. Then you can ask where the job stands.

Nailed on WhatsApp
  1. You: Paid the guys 1,000 on Klein
  2. Nailed: Log $1,000 labor on Klein, paid today?
  3. You: Yes
  4. Nailed: Saved ✅ $1,000.00 · Labor · Klein

Nailed tracks the numbers. Code does the math, not the AI, and an amount never changes without your tap. It doesn't bill hours for you or run payroll. It keeps receipts and costs where you can find them. The pricing page has the plan and the 14-day free trial (no card to try).

Frequently asked questions

Can I switch contract types halfway through a job?

Yes, if the homeowner agrees in writing before you change how you bill. Say what changes, from which date, and what has already been billed. Don't switch quietly after a loss shows up. That is how disputes start. Put the new terms on a signed change.

What is a not-to-exceed cap?

It's a ceiling on a time and materials or cost plus job. You bill actual cost, but the total can't pass the cap without the homeowner's written OK. It gives the client a number to plan around and gives you a clear moment to ask for more.

Do I need to show receipts on a cost plus job?

Plan on it. The homeowner is paying your actual costs, so they will want proof. Keep every receipt and sub invoice filed to the job from day one. Rebuilding that pile at the end is slow, and it makes clients doubt your numbers.

Which type is easiest for a first-time client to accept?

Fixed price. One number, one signature. Time and materials and cost plus ask the homeowner to trust the final bill, which is harder with someone new. A cap on either one helps a lot.