How to Price a Remodeling Job: Costs, Overhead, Profit

By Roy, Founder of Nailed. Published · Updated . 7 min read.

Nailed writes the quote from a voice note you send from the truck. Try it free

To price a remodeling job, add up what the job costs you directly, then add your overhead and your profit as shares of the price. Divide the direct cost by what's left after overhead and profit. That number is the price. Then check it against jobs you've already done.

The next sections do it with real numbers: a basement finish that comes to exactly $40,000.00, and what a flat 20% markup would have done to it.

What are the steps to price a remodeling job?

Five. One: add up direct costs, which is everything the job itself uses. Two: pick your overhead share of the price. Three: pick the net profit you want. Four: divide direct cost by what's left. Five: compare the result to your past jobs and your market.

Skip any one and the price is a guess. The order matters too. Direct costs come first, because they're the only part you can measure on this job.

What counts as a direct cost?

Anything the job uses up that you wouldn't pay for if you didn't have the job. Materials, labor, subs, permits, dumpster, rentals, and anything you buy for the job alone.

Labor goes in at your loaded rate, not the wage. The loaded rate includes payroll tax, workers comp, benefits and the hours nobody can bill. A carpenter paid $32.00 an hour costs you more than that, and the loaded labor rate calculator shows how much. The example below uses $58.00 an hour.

Here are the direct costs for a 600-square-foot basement finish. These are made-up numbers to show the math, not a price guide.

LineQtyUnitUnit costAmount
Permits and dumpster1LS$1,400.00$1,400.00
Framing lumber and insulation1LS$3,100.00$3,100.00
Drywall and finishing supplies1LS$2,400.00$2,400.00
LVP flooring600sf$4.20$2,520.00
Trim and doors1LS$1,680.00$1,680.00
Paint and primer1LS$520.00$520.00
Carpentry labor, loaded190hr$58.00$11,020.00
Electrical, sub1LS$3,600.00$3,600.00
HVAC extension, sub1LS$2,960.00$2,960.00
Direct cost$29,200.00

The materials add to $10,220.00. Labor is $11,020.00. The two subs are $6,560.00, and permits and dumpster are $1,400.00. Together that's $29,200.00.

How do you figure out your overhead?

Add up a year of costs that don't belong to any one job: rent, insurance, your truck, phone, software, office help, your own admin time. Divide by a year of revenue. That's your overhead share of the price.

The example uses 17%. For scale, NAHB's FY2024 survey of remodelers put operating expenses at 23.6% of revenue, with a 29.9% average gross margin and a 6.3% net. Those are averages, not targets. Your number comes from your own books. The markup and margin calculator has a "Build the bid" tab if you want to try different values.

How much profit should you add?

Pick a net profit as a share of the price, and treat it as a cost of staying in business. The example uses 10%. NAHB's 6.3% average is a reminder that plenty of remodelers keep less. Aim above what you need to survive, then protect it job by job.

Profit is what's left after every cost, including your own pay and the overhead. If you leave your own pay out, you aren't earning a profit, you're working for free.

How do you turn costs, overhead and profit into a price?

Divide the direct cost by one minus the overhead share minus the profit share. It's not "add 27% to cost." Overhead and profit are shares of the price, so you divide.

In the example: 1 - 0.17 - 0.10 = 0.73. Then $29,200.00 divided by 0.73 is $40,000.00 exactly.

LineAmountShare of price
Direct cost$29,200.0073.00%
Overhead$6,800.0017.00%
Net profit$4,000.0010.00%
Price$40,000.00100.00%

Check it: 17% of $40,000.00 is $6,800.00, and 10% is $4,000.00. $29,200.00 plus $6,800.00 plus $4,000.00 is $40,000.00.

The gross margin on this price is $10,800.00 over cost, which is 27.00% of the price. In markup terms, $10,800.00 over a $29,200.00 cost is 36.99%. That's the markup you actually need, and it's well above 20%.

What happens if you just add 20%?

You lose money, and the job looks fine. Take the same $29,200.00 and add 20%: $35,040.00. Your gross margin is $5,840.00, which is 16.67% of the price. Overhead at 17% of $35,040.00 is $5,956.80. That's more than the $5,840.00 you earned above cost.

You end up $116.80 in the hole. The client signed, the job got built, and the business paid you less than nothing for it. A flat markup works only when it happens to match your overhead and profit. Most of the time it doesn't.

How do you gut-check the price?

Divide by the square feet and compare to your past jobs. $40,000.00 over 600 sf is $66.67 a square foot. Is that in line with the last three basements you finished? If it's far off, find out why before you send it.

Don't use a number from a book or a neighbor. It knows nothing about your costs or your market. Your own finished jobs, by code, are the best source, which is what job costing gives you. That only works if you track expenses per job while the job runs.

Then check what the other side sees: does the scope match what they asked for, are allowances placed where they haven't chosen, and are exclusions written down? The kitchen remodel estimate template shows how to lay out lines, allowances and exclusions on the page.

What do you do about the things you can't see?

Decide how you'll handle them before you price. Either carry a visible contingency line the client can see and get credited back, or write an exclusion for hidden conditions and price any surprise by change order when you find it.

Both are honest. Pretending the walls will be fine is not. If you carry contingency, say what it covers. If you use exclusions, say it in plain words before they sign. See how to get change orders signed for the timing.

How do you set the payment schedule?

Before you send the price, split it into draws tied to milestones. On the $40,000.00 basement, 10% at signing is $4,000.00, and three draws of 30% are $12,000.00 each. They add to $40,000.00.

Several states cap the deposit a contractor can take, so check yours first. The contractor payment schedule template has full schedules for three job sizes.

Can you price a job from a voice note?

Yes, with a catch: the prices are yours. You say the numbers, Nailed drafts the quote, you read it, and nothing goes to the client until you tap send. Nailed doesn't invent a price, and the totals come from code, not from the AI.

Nailed on WhatsApp
  1. You: Voice note (0:26): Basement finish for the Lees, 600 feet. Price is 40,000. 10 percent down.
  2. Nailed: Got it. Draft quote, Lee basement finish: Total: $40,000.00 Deposit at signing (10%): $4,000.00 Want me to break it into lines first, or send it as is?

Read how it works on the how it works page, or what an AI office manager does for a small GC.

A pricing worksheet you can copy

Remodel pricing worksheet (copy and fill in)

JOB: [name, address]

  1. DIRECT COSTS Materials: $[ ] Labor: [ ] hours x $[loaded rate] = $[ ] Subcontractors: $[ ] Permits, dumpster, rentals: $[ ] DIRECT COST: $[ ]

  2. OVERHEAD (share of price): [ ]%

  3. NET PROFIT (share of price): [ ]%

  4. PRICE = direct cost / (1 - overhead - profit) = $[ ] Check: overhead $[ ] + profit $[ ] + direct cost $[ ] = price

  5. GUT CHECK Price per square foot: $[ ] Last similar job per square foot: $[ ] Allowances placed: [list] Exclusions written: [list]

PAYMENT SCHEDULE: [10]% at signing $[ ]; [ ]% at [milestone] $[ ]; balance at completion $[ ]

Want the quote, the signature and the payment follow-ups off your plate? See what Nailed does for small contractors, or the pricing page.

How you charge matters as much as the number. Compare fixed price vs time and materials vs cost plus before you quote.

Frequently asked questions

How do contractors price a remodeling job?

They add up direct costs (materials, labor, subs, permits), then add overhead and profit as shares of the price. Divide direct cost by what's left after overhead and profit, and that's the price. Then they check it against similar past jobs.

Should I price by the square foot?

As a gut check only. Price from the parts of the job, then divide by the square feet and compare to your past jobs. A square-foot number from a book or a neighbor knows nothing about your costs, your market or the house.

How much contingency should I add?

Enough to cover what you can't see, and no more. Older houses and open walls get more. Some GCs show it as a line the client can see, and credit back what they don't use. Others use an exclusion and a change order instead.

Do I charge for estimates?

That's your call. Some contractors give simple estimates free and charge a design or scoping fee for complex jobs, then credit it to the contract. Whatever you pick, tell the client before you start, not after.

What if my price is higher than the other bids?

Don't drop it without a reason. Check your numbers, then compare scope line by line with the other bid. Often the cheaper one leaves out something yours includes. If your costs and overhead are real, a lower price is a loss, not a deal.