How to Quote a Bathroom Remodel (Worked Example)
Nailed writes the quote from a voice note you send from the truck. Try it free
To quote a bathroom remodel, price the wet-area work as its own lines, make everything the client picks an allowance, and write down what happens when you open the wall. A small bath is mostly tile, plumbing and surprises, so the fine print matters more than the total. The worked example below uses made-up numbers. Swap in your own rates.
What do you check on a walkthrough before quoting?
The things you can't fix cheaply later. Measure the floor and the wet walls in square feet. Look at the drain location, the shutoff valves, the fan and its duct, the age of the wiring, and the floor under the tub or toilet. Press on it. Soft is a line in your notes.
Ask who buys the vanity, the toilet and the glass, and whether the client wants the layout moved. Moving a drain is the line that changes a bathroom quote most.
How do you build the line items?
Trade by trade, with a quantity, a unit and a unit price on each line. Use a lump sum only where a count makes no sense, like demo. Here is a 5x9 hall bath, with the client buying the vanity and the glass door chosen later.
| Item | Qty | Unit | Unit price | Amount |
|---|---|---|---|---|
| Demo and haul-away | 1 | LS | $1,200.00 | $1,200.00 |
| Backer board and waterproofing, wet walls | 80 | sf | $9.00 | $720.00 |
| Shower pan membrane and flood test | 1 | LS | $650.00 | $650.00 |
| Tile labor, floor and walls | 120 | sf | $18.00 | $2,160.00 |
| Tile material (ALLOWANCE) | 120 | sf | $7.00 | $840.00 |
| Vanity and top (ALLOWANCE) | 1 | LS | $900.00 | $900.00 |
| Vanity install | 1 | LS | $350.00 | $350.00 |
| Toilet install | 1 | LS | $220.00 | $220.00 |
| Shower valve and trim, rough-in and set | 1 | LS | $1,150.00 | $1,150.00 |
| Electrical: fan, GFCI, vanity light | 1 | LS | $780.00 | $780.00 |
| Glass shower door (ALLOWANCE) | 1 | LS | $1,400.00 | $1,400.00 |
| Paint | 1 | LS | $550.00 | $550.00 |
| Permit fee | 1 | LS | $300.00 | $300.00 |
| Dumpster | 1 | LS | $450.00 | $450.00 |
| Total | $11,670.00 |
Check one: 80 sf at $9.00 is $720.00, and 120 sf at $18.00 is $2,160.00. The fourteen lines add to $11,670.00. For a copy-paste layout with the clauses, see the bathroom remodel estimate template.
Why price waterproofing as its own line?
Because the client can't see it once the tile is up, and it's the part that fails expensively. A separate line shows you priced it, and it stops the waterproofing from being the first thing cut when the budget gets tight.
Tile gets the same treatment: labor per square foot, material as an allowance per square foot. If the client picks a tile above the allowance, the difference times the square footage goes on a signed change order before you order it.
What do you write about hidden conditions?
Pick a rule and put it on the quote. Price the job assuming the subfloor and walls are sound, list repair under exclusions, and give a unit price for repair, per sheet of subfloor or per square foot, so the client knows the cost before you open anything.
When you find rot, stop and price it in writing before you fix it. The change order template has wording, and how to price a change order shows the math.
How should you split the payments on a small job?
Fewer draws, tied to what the client sees. This example uses 25% at signing, 50% when the tile is set and the remainder at completion on the $11,670.00 total.
| Draw | When | Amount |
|---|---|---|
| 1 | At signing (25%) | $2,917.50 |
| 2 | Tile set (50%) | $5,835.00 |
| 3 | Completion (remainder) | $2,917.50 |
| Total | $11,670.00 |
Some states cap the deposit, so check yours before you set the first draw. This is general information, not legal advice. See how much deposit a contractor can ask for.
Can you turn your notes into the quote?
Yes. Write the notes on site, a price on each item, and paste them into the free quote maker. It builds the lines, adds them in code, and gives you a PDF with a deposit schedule. No sign-up, nothing saved.
Hall bath, 5x9, client buys the vanity. Demo and haul 1,200 Backer and waterproofing 80 sf at 9 Shower pan membrane and flood test 650 Tile labor 120 sf at 18 Tile allowance 120 sf at 7 Vanity allowance 900, install 350 Toilet install 220 Shower valve 1,150 Electrical 780 Glass door allowance 1.4k Paint 550, permit 300, dumpster 450
Read the draft, add your exclusions and a valid-until date, then send it. If you want the quote, the signature and the payment follow-ups in one place, that's Nailed: 14 days free, no card. See pricing. Want the wider picture first? Read how to write a contractor estimate.
Frequently asked questions
How do you quote a bathroom remodel?
Measure the room and the wet walls, list every scope item with a quantity, price tile as separate lines for waterproofing, labor and material allowance, set allowances for fixtures the client picks, list exclusions, and split the payments. Add the lines in a tool and check the total.
What do you include in a bathroom remodel quote?
Demo, plumbing, waterproofing and backer, tile labor and material, vanity and fixtures, electrical, paint, dumpster and permit. Then allowances, exclusions for hidden conditions like rot and subfloor repair, a payment schedule and a date the price is good until.
How do you quote tile on a bathroom?
As three lines. Backer and waterproofing, labor to set the tile per square foot, and the tile itself as an allowance per square foot. That way a client who picks a pricier tile changes one line, and the waterproofing can't get trimmed in a budget cut.
What if the subfloor or wall is rotten?
Say so before it happens. Price the job assuming it's sound, list repair as an exclusion, and give a unit price for repair so the client knows the cost before you open the wall. When you find it, write the change order before you fix it.
Can I make a bathroom quote from my notes?
Yes. Paste your walkthrough notes, with a price on each item, into the free quote maker. It builds the lines, adds them in code and returns a PDF with a deposit schedule. Review it and add your exclusions before sending.