Construction Allowances Explained for Contractors
Nailed writes the quote from a voice note you send from the truck. Try it free
An allowance is a set dollar amount inside the contract price for something the client has not chosen yet, such as tile or a light fixture package. If the real cost comes in higher, the client pays the difference. If it comes in lower, the client gets a credit, as long as the contract says so.
What is an allowance in a construction contract?
An allowance is a placeholder price for a selection the client will make after signing. You carry a number so the quote can be complete. The contract says the final price follows the real cost: more if the choice costs more, less if it costs less.
It exists because clients rarely pick tile before they hire you. Without it, you either leave the item off the quote, which makes your price look low, or you guess and eat the difference. See the glossary entry for the short version.
Who pays when the selection costs more?
The client, if the contract says so. That is the whole point of an allowance. If the contract is silent, expect an argument, and expect to lose it, because the price you quoted "included tile."
Two things make the overage collectible. The allowance has to be its own line, and the client has to see the actual number before you buy. A text of the receipt or the supplier quote, answered with "ok", beats a verbal "sure, go ahead."
Who gets the money when it costs less?
The client gets a credit, unless your contract says otherwise. Be careful about writing "contractor keeps any savings". Some contracts do it, but it turns your allowance into padding and clients notice. A clean credit costs you a little and buys a lot of trust.
Whichever way you write it, write it the same for over and under. A clause that only works in one direction reads as a trap.
What is the difference between a material allowance and an installed allowance?
A material allowance covers the product only. An installed allowance covers product and labor. Material is easier to price and to reconcile. Installed is easier for the client to read, but a heavier tile can double your labor, so the allowance stops meaning anything.
My view: allow the material, price the install as its own firm line, and say so. In the example below, tile install is $18 a square foot on its own line and does not move.
Worked example: a tile allowance, over and under
Here is the quote line, then two different client choices. Every number is a made-up example.
The quote carries a tile allowance of $8.00 a square foot for 120 square feet, covering tile and setting materials. Allowance: 120 x $8.00 = $960. Installation is a separate firm line at $18 a square foot, so 120 x $18 = $2,160, and it is outside the allowance.
Case 1, the client picks $11.50 tile. Order 10 percent extra for cuts: 120 x 1.10 = 132 square feet. Tile: 132 x $11.50 = $1,518. Thinset, grout and membrane: $240. Actual cost: $1,518 + $240 = $1,758. Overage: $1,758 - $960 = $798. Your contract adds 15 percent markup to allowance overages: $798 x 0.15 = $119.70. Change order: $798 + $119.70 = $917.70.
Case 2, the client picks $4.75 tile. Tile: 132 x $4.75 = $627, plus $240 = $867. Underage: $960 - $867 = $93 credit, at cost.
Notice what the waste factor did. The allowance was figured on 120 square feet, but you buy 132. Say in the clause whether waste is inside the allowance. If you forget, the client's $11.50 tile is "only $3.50 over", and the $798 is a fight.
ALLOWANCE RECONCILIATION Job: [name, address] Date of selection: [date]
Item: Tile allowance (material and setting supplies) Allowance in contract: 120 sq ft x $8.00 = $960.00 Selected: [tile name], $11.50/sq ft, 132 sq ft ordered (includes 10% waste) Actual cost: tile $1,518.00 + setting supplies $240.00 = $1,758.00 Difference over allowance: $798.00 Markup per contract (15%): $119.70 Change in contract price: +$917.70
Client approval: ______________ Date: ________
For how to price and word the change itself, see how to price a change order and the change order template.
How do I write an allowance line in a contract?
Name the item, the quantity, the unit price and what is covered. State who pays the difference and when the client must choose. Three versions, from simplest to strongest:
-
MATERIAL ONLY Tile allowance: $8.00 per sq ft x 120 sq ft = $960.00. Covers tile only. Installation, setting materials and waste are not included. Actual cost above or below the allowance will be added to or deducted from the contract price.
-
INSTALLED Tile allowance, installed: $26.00 per sq ft x 120 sq ft = $3,120.00. Covers tile, setting materials and installation of a standard layout. Patterns, diagonal layouts or large-format tile may change the installation price. Any difference will be added or deducted by written change order.
-
WITH A DEADLINE Tile allowance: $8.00 per sq ft x 120 sq ft = $960.00, material and setting supplies, 10% waste included. Owner will select by [date]. If the selection is made after that date, the schedule moves day for day and the owner agrees to any resulting cost. The difference between actual cost and the allowance, plus 15% overhead and profit, will be added to or deducted from the contract price by change order signed before ordering.
Version 3 is the one that saves you. The deadline is what stops a tile choice from turning your finish date into your problem.
How much of a quote should be allowances?
There is no standard number. I did not find a primary source that gives one, and I will not make one up. Add your allowances up and compare them to the price.
On a $31,000 bath, a $960 tile allowance, a $1,300 vanity and fixtures allowance and a $600 lighting allowance total $2,860. That is 9.2 percent of the price. A quote where a third of the price is still a guess is an estimate in disguise. See estimate vs quote vs bid vs proposal.
Allowance, contingency or TBD line: which one do I use?
Use an allowance when the item is known and the price is not. Use a contingency for problems nobody can see yet. Use a TBD line when you cannot responsibly price it at all. Each one goes on its own line, with its own rule for who pays when it moves.
The mistake is mixing them. If the tile overage comes out of the contingency, you have nothing left when the subfloor is rotten.
What does it look like when the allowance blows past?
It looks like the "ok" you did not get. The client picks the $22-a-foot tile, you order it, and the invoice arrives with nothing signed. The job losing money warning signs checklist has this as sign 5. The fix is to compare the allowance to the real number the day the selection is made, not on the supplier's invoice.
Nailed helps with the voice-note part of this. You say the allowance and it comes back as its own line on the quote, which you review before anything is sent. The client e-signs from a link. Receipts you photograph land on the job, so the actual number is there when you need it. The AI does not do the math, and nothing changes in an amount without your tap. Change orders are coming soon, so for now a reconciliation like the one above goes out as a revised quote or on your own form.
- You: Voice note (0:31): Reyes bath. Tile allowance, 120 square feet at 8 a foot. Tile install is 18 a foot, separate.
- Nailed: Got it. Two lines for the Reyes bath: Tile material allowance: 120 sq ft at $8.00 = $960.00 (allowance) Tile installation: 120 sq ft at $18.00 = $2,160.00 Tap Send to email the quote for signature, or tell me what to change.
- You: Send it
Read how it works or what an AI office manager does for a small GC. The kitchen remodel estimate and bathroom remodel estimate both show allowance lines in a full quote.
Frequently asked questions
What percent of a contract should be allowances?
There is no standard number. Add them up on your own quote. The more of the price that is a guess, the less your price means. If allowances are a big slice of the job, push the client to choose before you sign.
Is an allowance the same as a contingency?
No. An allowance is a known item with an unknown price, like tile not yet picked. A contingency is money held for unknown problems, like rot behind a wall. Write them as separate lines so a tile upgrade never eats the cushion.
Can I add markup to an allowance overage?
Only if the contract says so. If your price includes your markup on the allowance, the overage should carry the same markup, and the clause should say it. Silence usually means you eat it, so decide before you send the quote.
What if the client never picks anything?
Put a selection deadline in the contract and say what happens when it passes: the schedule slides, or you buy at the allowance price. Without a date, a late tile choice becomes your delay, and the days cost you money.