Is Your Job Losing Money? 5 Early Signs and a Quick Check
Nailed files every receipt to the right job and tells you what each one is making. Try it free
You can tell a job is losing money before it ends by checking one thing: whether the share of the budget you've spent is ahead of the share of the work you've finished. If you're 60% done and you've spent 71% of the cost budget, you're headed for a loss of margin. Take what you've spent, divide by percent complete, and you have your projected final cost.
How do you know a job is losing money before it's over?
Run the ten-minute check. You need three numbers: what the job cost so far, how far along it is, and the contract price. Then do one division.
Projected final cost = cost to date / percent complete
Projected profit = contract price - projected final cost
This is a common method in project accounting, and it's a rough one. It assumes the rest of the job will cost the same per percent as the part you've already done. That's usually fair, and when it isn't, it's usually worse, not better, since the punch list drags on.
Here's the check on one real-shaped job. A remodeler signs a $42,000 job with a cost budget of $31,500. That's $10,500 of planned profit, a 25.00% gross margin. NAHB's latest remodeler average is 29.9% gross, so 25% is a realistic plan for a small shop.
At about 60% complete, the books show $22,300 spent.
- Spent against budget: 22,300 / 31,500 = 70.8%
- Done: 60%
- Burn ratio: 70.8 / 60 = 1.18
- Projected final cost: 22,300 / 0.60 = $37,166.67
- Projected profit: 42,000 - 37,166.67 = $4,833.33
- Projected margin: 4,833.33 / 42,000 = 11.51%
Planned 25%. Heading for 11.5%. That's $5,666.67 of profit gone, and the job isn't done yet. At 60% you can still do something about it. At 100% you can only write it down.
A burn ratio of 1.0 means you're on pace. Above 1.1, look hard. The five signs below are why.
Sign 1: Are you spending faster than you're finishing?
That's the burn ratio above. If you've spent 70% of the money and finished 60% of the work, something cost more than you planned, and it won't fix itself.
Common causes: materials priced a season ago, a second trip for the part that was wrong, a sub who needed two visits, a crew that's slow on this particular kind of work. Open the cost log and find the line that jumped. Usually it's one or two.
The only way to see it is to have the costs logged against the job. If you're still working from memory, start with how to track expenses per job. It takes a photo and a job name.
Sign 2: Is there work on site nobody priced?
The client asked for the niche to be 6 inches deeper. You moved a drain because the joist was in the way. Somebody wants a second outlet "while you're in there." Each one is small. Each one is also unbilled until you write it up.
Add up the extras that happened without a signed change. That's money you're spending and not charging for. In the example above, if $3,000 of the overrun is extras that never got priced, you've found half your problem, and you can still recover it by writing the change order today.
Get the price agreed before the work happens, which is much easier than after. The guide to getting change orders signed covers how, and the change order template has the wording.
Sign 3: Are labor hours ahead of plan?
Hours tell you before dollars do. Dollars lag, since payroll lands a week later. Hours you can count today.
Say you budgeted 300 hours at $48, which is $14,400. At 60% done, your crew has logged 215 hours. Divide 215 by 0.60 and you get a projected 358 hours. That's about 58 hours over, or roughly $2,800 at $48 an hour.
Nobody had to do payroll to know that. If you track hours, you'll know it at the end of the second week and not the end of the job. Hours also point at the cause: a bad estimate, a slow phase or rework.
If your $48 is a guess, check it. The labor rate calculator shows what a worker really costs once taxes and insurance are in.
Sign 4: Have you billed less than the work you've done?
Billing behind progress is a cash problem that looks like a profit problem. You're 60% done and you've billed 40%. You've paid for the lumber, the crew and the sub, and the client owes you for work you haven't invoiced.
This one doesn't mean you're losing money. It means you're financing the client, and any cost surprise now hits your cash before it hits your margin. Check your payment schedule against the real progress. The contractor payment schedule template has three examples.
The opposite problem matters too. If you've billed far more than you've done, you're holding the client's money for work that isn't finished, and the last 20% of the job is where the trouble lives. Ahead of progress on billing is comfortable. It can also hide a bad margin until the last check.
Don't confuse cash with profit. A full bank account tells you nothing about this job.
Sign 5: Did an allowance blow past its number?
Allowances are numbers you guessed before the client picked anything. Tile at $8 a foot, a vanity at $900, a faucet at $250. Then the client falls for the $22-a-foot tile.
If the contract says the client pays the difference, you're fine, as long as you said so in writing and told them when they chose. If it doesn't, the overage is yours. Compare each allowance line to its actual, the day the selection is made. Not on the invoice.
Kitchens and baths blow allowances most often. The kitchen remodel estimate template and the bathroom remodel estimate template show allowance lines written so that the overage has a clear owner.
What do you do when the answer is bad?
Act this week. Four moves, in order:
- Stop and price the extra work. Anything not in the contract gets a number and a signature before more of it happens.
- Call the client. Plainly, with the number. Clients take "this addition is $1,850" far better than a surprise at the end.
- Re-plan the rest of the job. Look at the remaining phases for hours you can pull back. Don't cut quality to rescue a number.
- Re-run the check next week. If the burn ratio isn't coming down, you haven't fixed it yet.
Two lines you can send:
Hi [Name], while we were in the wall we found [issue]. Fixing it adds $[amount] and [X] days. I'll send the change order now. I can't start that part until you've signed it.
[Job]: spent $[X] of $[budget]. [Y]% done. Projected final cost $[X / Y]. Margin planned [A]%, projected [B]%. Action: [one thing].
None of this is a reason to be nervous. Every job drifts. The shops that stay in business are the ones that notice at 60%.
How can you see this without doing math every Friday?
Keep your costs logged as they happen, and let something else hold the running number. That's the idea behind Nailed. You text receipts and costs to the job as they come in, and you can ask "how am I doing on the Alvarez bath?" at any time. It also nudges you when a job's margin drops below what you quoted.
- Nailed: Heads up on the Klein kitchen: costs are running ahead and the margin is now under what you quoted. The biggest jump is materials. Want the breakdown?
- You: Yeah show me
- Nailed: Quoted $42,000. Costs logged so far: $22,300. Materials is running over its estimate more than any other line. Was the east wall extra work in the quote?
- You: Right, I never wrote that up. Doing it tonight.
The numbers come from the costs you logged and the quote you sent. Nailed doesn't invent a price, and nothing about a job's money changes until you approve it. The percent-complete call is still yours, since you're the one standing in the house. See how it works, or read about the AI office manager for contractors.
For what a healthy margin looks like and how to price one in, read the general contractor profit margin guide. To turn a margin target into a price, the markup and margin calculator does the conversion.
Frequently asked questions
How often should I check whether a job is losing money?
Weekly, on the same day. It takes ten minutes once your costs are logged. Checking only at the end tells you what happened. Checking weekly lets you change it. A slip caught at 30% done costs a phone call. At 90% done it costs you the profit.
What if percent complete is hard to pin down?
Use milestones, not gut. For a bath: demo, rough plumbing, tile, fixtures, punch list, each with a share of the job. Be a little pessimistic. An honest 55% beats a hopeful 70%. Re-run the check weekly so one bad guess doesn't hang around.
Does a healthy bank balance mean the job is profitable?
No. Deposits and progress payments are cash, not profit. A job can be fully paid on schedule and still lose money, because the check size was set by the contract and the cost was set by the work. Compare costs to the budget, not cash to cash.
What margin should a job have at the halfway point?
The same as you planned. If you priced a 25% margin, a job at 50% done should be on track for 25%, with half the cost spent. A projected margin below plan at any point means the final number will be lower unless something changes.