Job Cost Sheet Template (Filled Example With Profit)

By Roy, Founder of Nailed. Published . 6 min read.

Nailed files every receipt to the right job and tells you what each one is making. Try it free

A job cost sheet is one page per job that lists what you expected to spend, what you have committed, what you have actually spent, and where it will land. It ends with the number that matters: profit and margin. A filled example for a $42,000 bathroom is below, plus a blank version to copy.

What goes on a job cost sheet?

Four things: the contract price at the top, a short list of cost categories, a column each for budget, committed, actual and forecast, and profit and margin at the bottom. Add the job name, address and date. Nothing else is required, and every extra column is one more thing you will skip.

Budget comes from your estimate, line by line. If you built the quote well, the budget column is already written. If you need a model for the estimate, see the construction estimate template.

Job cost sheet example: a $42,000 bathroom

This is a made-up job, filled in the way it looks about two thirds through. Tile is already over. Plumbing turned up old galvanized pipe behind the wall. Labor will run three extra days.

Job cost sheet: filled example

JOB COST SHEET Job: Reyes bath remodel, 418 Alder St Contract price: $42,000 Date posted: [date]

Category | Budget | Committed | Actual to date | Forecast final Demo and haul-off | $1,800 | $1,800 | $1,800 | $1,800 Plumbing (sub) | $4,200 | $4,650 | $3,100 | $4,650 Tile and setting materials | $5,600 | $6,100 | $6,100 | $6,100 Electrical (sub) | $1,900 | $1,900 | $950 | $1,900 Fixtures and vanity | $3,900 | $3,900 | $3,675 | $3,900 Labor (own crew) | $14,000 | $14,000 | $9,800 | $14,600 Dumpster | $450 | $450 | $450 | $450 Permit | $380 | $380 | $380 | $380

TOTAL COST | $32,230 | $33,180 | $26,255 | $33,780

Contract price: $42,000 Profit at budget: $9,770 (23.3% margin) Profit at forecast: $8,220 (19.6% margin) Markup on forecast cost: 24.3% Over budget: $1,550

The arithmetic, so you can check it. Budget adds up to $32,230. Forecast adds up to $33,780, which is $1,550 more: plumbing +$450, tile +$500, labor +$600. Price minus forecast cost is $42,000 - $33,780 = $8,220. Divide by the price and you get a 19.6% margin. Divide by the cost and you get a 24.3% markup. Same dollars, two different percentages.

Blank job cost sheet to copy

Paste this into a note, a doc or a spreadsheet. Change the categories to match your trade.

Job cost sheet: blank

JOB COST SHEET Job: [name, address] Contract price: $[ ] Change orders signed: $[ ] Total price: $[ ]

Category | Budget | Committed | Actual to date | Forecast final Demo and haul-off | | | | Plumbing | | | | Electrical | | | | Framing and drywall | | | | Tile and flooring | | | | Fixtures and cabinets | | | | Paint | | | | Labor (own crew) | | | | Dumpster and rentals | | | | Permits | | | | Other | | | |

TOTAL COST | | | |

Total price - forecast cost = profit: $[ ] Profit / total price = margin: [ ]% Profit / forecast cost = markup: [ ]%

How do I set up a job cost sheet for a small remodel?

Copy the budget from your estimate, one line per category. Add change orders to the price when they are signed, not when you think about them. Then keep the committed and actual columns current. That is the entire setup, and it takes about ten minutes per job.

If you have no category list yet, the job costing guide has a starter set and a worked bath job.

What is the difference between committed and actual cost?

Committed is what you have agreed to pay. Actual is what has been paid or receipted. A sub quote of $4,650 is committed on the day you accept it, even if he bills in three weeks. Looking only at actual is why a plumbing overrun shows up as a surprise at the end.

In the example, plumbing actual is $3,100 but committed is $4,650. The sheet is already telling you the category is $450 over, and the sub has not finished.

How do I turn the sheet into profit and margin?

Take the contract price, plus signed change orders, and subtract the forecast cost. That is profit in dollars. Divide by the price for margin. Divide by the cost for markup. Margin is always the smaller number, and it is the one that tells you what you keep from each dollar billed.

Do this on the forecast column. Profit at budget is a hope. Profit at forecast is the number you are managing. Check any price against your target with the markup and margin calculator, and see general contractor profit margin for how it relates to overhead.

How often should I post costs?

The day the receipt is in your hand. Weekly is the outer limit. A tile order you posted three weeks late is a number you could not have acted on when it mattered.

That is also where sheets die. Receipts live in the truck, the typing happens on Sunday, and by the third job nobody updates anything. A sheet is only as good as its last entry.

When does a spreadsheet stop working?

When you are running several jobs and the receipts pile up faster than you type. One honest rule: if you have skipped two weeks of entries on any job, the sheet is stale, and a stale sheet is worse than none because you still trust it.

A spreadsheet is fine for one or two jobs at once. Past that, the weak point is the data entry, not the formulas.

How does Nailed fill in the actual column?

You take a photo of the receipt and say which job it belongs to. Nailed reads the supplier, the date and the total, asks you to confirm, and files it to that job. It also shows profit per job and warns when a margin is slipping. It does not track crew hours or run payroll, so labor from your own crew still comes from you.

Nailed on WhatsApp
  1. You: [photo of supplier receipt]
  2. You: Reyes bath
  3. Nailed: Got it. Tile supplier, Nov 11, $612.40. Filing it to the Reyes bath under materials. Right?
  4. You: Yep
  5. Nailed: Saved. Reyes bath is at $26,255.00 in costs against a $42,000.00 quote.

The totals come from code, not from the AI, and each receipt waits for your confirmation before it is saved. Read how it works, or see what an AI office manager does for a small GC. Pricing is on the pricing page.

For the whole receipts routine, see how to track expenses per job from your phone. If a job is drifting, warning signs a job is losing money is the checklist.

Frequently asked questions

How often should I update a job cost sheet?

Post costs the day they happen, or at worst once a week. A sheet you fill in at month end tells you what already went wrong. Receipts are the main thing to post fast, because a lost receipt is lost profit you will never see.

What is the difference between committed and actual cost?

Committed is money you have agreed to spend but not yet paid: a signed sub quote, a tile order, a rental. Actual is what has been paid or receipted. Watching committed catches a bad number weeks before the bill lands.

Do I need CSI cost codes on a small remodel?

No. CSI codes are built for large projects with dozens of trades. A two or three person shop does better with eight to ten categories it will really fill in: demo, plumbing, electrical, tile, fixtures, labor, dumpster, permits and a few more.

When does a spreadsheet stop working for job costing?

When you have several jobs running and the receipts pile up in the truck. The sheet is not the problem, the typing is. Once you skip a week of entries, the numbers go stale and you stop trusting the sheet at all.