Construction Proposal Template (Free) With Clause Notes
Nailed writes the quote from a voice note you send from the truck. Try it free
A construction proposal is a fixed price for a defined scope: what you'll build, what you won't, what it costs, when the money is due, and what happens when something changes. Copy the template below, then read the note on each clause. A filled construction proposal example (an $18,717 deck replacement, math checked) follows the template.
What should a construction proposal include?
Ten things: who you are, who it's for, the scope of work, what's excluded, the price by line, allowances, the payment schedule, the timeline, how changes are handled, and a signature line with an expiry date. Add your license number, insurance and warranty if your state or your clients want them.
If you can't fit it on two pages, you're probably explaining things the scope should have made obvious.
Copy-paste construction proposal template
Plain text, numbered sections. Paste it into Word, Google Docs, an email or a text. Fill in the brackets and delete what doesn't apply.
PROPOSAL #[number]
Date: [date] Valid until: [date, 15 to 30 days out]
-
CONTRACTOR [Business name] [Phone] | [Email] License #: [number, if your state requires one] Insurance: [carrier and policy #]
-
CLIENT AND PROJECT Client: [name] Project address: [address] Project: [one line, e.g. Replace 14x16 deck]
-
SCOPE OF WORK We will:
- [Verb + quantity + material, e.g. Demolish existing 14x16 deck and haul away]
- [Install 8 concrete pier footings]
- [Frame with pressure-treated joists and beams, 224 sf]
- [Install composite decking, 224 sf, color: ____]
- [Install composite railing, 44 lf]
- [Build stairs, 5 risers, with railing]
- [Pull permit and schedule inspections]
- EXCLUSIONS Not included unless added by change order:
- [Electrical, lighting, outlets]
- [Landscaping and repair of lawn or plantings]
- [Repair of rot or damage found in the house band board]
- [Anything not listed in section 3]
-
ALLOWANCES [Item]: $[amount] allowance, supply only. If the final cost is higher or lower, the difference is added or credited on the final invoice. [None]
-
PRICE [Line items table: item, qty, unit, unit price, amount] Total: $[amount] This price includes [labor, materials, permit, dumpster]. It does not include [sales tax / financing / ____].
-
PAYMENT SCHEDULE
- Deposit at signing: $[amount]
- Final payment on completion and walkthrough: $[amount] Each payment is due within [3] days of the invoice. Payment methods: [check, ACH, card]. [Late payments: state any late fee here only if your state allows it and you wrote it before the work.]
-
CHANGES Any change to scope, price or schedule must be in a written change order signed by both parties before the extra work begins. The change order will show the cost, the days added or removed, and the new contract total.
-
HIDDEN CONDITIONS If we find conditions that could not be seen at the time of this proposal (rot, concealed wiring or plumbing, soil problems, code issues), we will stop that part of the work, photograph the condition, and send a written change order before continuing.
-
SCHEDULE Start: about [date], after permits and material delivery. Finish: about [number] working days after start. Weather, inspection timing, material delays and client changes can move these dates. We will tell you as soon as we know.
-
PERMITS AND INSPECTIONS We pull the permits. The permit fee is in the price. [Client] provides access to the site on working days.
-
CLEANUP We clean up daily and haul away our debris at completion.
-
WARRANTY We warrant our workmanship for [1 year] from completion. Manufacturer warranties on materials pass to the client. This warranty does not cover normal wear, misuse, or damage from others.
-
CANCELLATION [If the client cancels before work starts: state what is refunded and what is kept for materials ordered and time spent.] [If this proposal was signed at the client's home, attach the notice of the right to cancel that your state and federal rules require.]
-
ACCEPTANCE By signing, the client accepts this proposal, including the price, scope, exclusions and terms above. This proposal expires on [date].
Client signature: ____________ Date: ______ Contractor signature: ____________ Date: ______
Why is each clause in there?
One line each. Know why it exists and you'll know when to bend it.
| Clause | Why it's there |
|---|---|
| Scope | It's the promise. If it's not here, it wasn't promised, in either direction. |
| Exclusions | Clients assume. This line stops "I thought lighting was included." |
| Allowances | Prices you can't know yet (tile, fixtures) get a placeholder and a rule for the difference. |
| Price and what it includes | Say if permit, dumpster and tax are in. It's the question you'll get on day three. |
| Payment schedule | Ties your cash to progress the client can see. |
| Changes | Makes the written change order the only way the price moves. |
| Hidden conditions | Rot and surprises are normal. This turns them into a process, not a fight. |
| Schedule | "About" dates and the reasons they slip. You're not promising a day you don't control. |
| Permits | Who pulls them, who pays, who lets the inspector in. |
| Insurance and license | Clients check. Some states require the number on the contract. |
| Warranty | States how long you stand behind the work, and what you don't. |
| Cleanup | Small, but it's the last thing the client sees. |
| Cancellation | What happens to the money if the client backs out. If you sell at the client's home, the FTC's Cooling-Off Rule may require a written notice of the right to cancel within three business days. |
| Acceptance and expiry | Turns the document into a deal, and stops a six-month-old price from coming back at you. |
Construction proposal example: a filled-in deck replacement
Here's a deck replacement, 14x16, composite decking. Quantities and units on every line, so nobody can argue "new deck". These are made-up numbers, not a price guide. Prices in your area will differ.
| Item | Qty | Unit | Unit price | Amount |
|---|---|---|---|---|
| Demo existing deck, haul-away | 1 | LS | $1,800.00 | $1,800.00 |
| Footings, concrete piers | 8 | ea | $310.00 | $2,480.00 |
| Framing, PT joists and beams | 224 | sf | $16.00 | $3,584.00 |
| Composite decking, supply and install | 224 | sf | $24.00 | $5,376.00 |
| Railing, composite | 44 | lf | $68.00 | $2,992.00 |
| Stairs, 5 risers, with railing | 1 | LS | $2,100.00 | $2,100.00 |
| Permit | 1 | LS | $385.00 | $385.00 |
| Total | $18,717.00 |
Payment schedule at 10/30/30/30:
| Payment | When | Amount |
|---|---|---|
| Deposit | At signing | $1,871.70 |
| Draw 1 | Footings and framing done | $5,615.10 |
| Draw 2 | Decking installed | $5,615.10 |
| Final | Railing, stairs, inspection passed | $5,615.10 |
| Total | $18,717.00 |
Four payments add back to the price to the cent. When the split doesn't divide evenly, put the odd cents on the last payment. More on that in the contractor payment schedule template.
How do you write the scope of work so it can't be argued?
Start every line with a verb. Add a quantity and a material. Name the color or model when it matters.
- Weak: "New deck."
- Better: "Install 224 sf composite decking, [brand/color], over PT framing, hidden fasteners."
Then write the exclusions as carefully as the scope. The line that saves you most often is the plain one: "Anything not listed in section 3 is not included."
Photos help. Take them at the walkthrough and attach the ones that show the existing condition.
What's the difference between a proposal, an estimate and a contract?
| Document | What it is | Binding? |
|---|---|---|
| Estimate | Your best guess at cost, often a range. | Usually not. Say so on the page. |
| Proposal | A fixed price for a defined scope, with terms. | Not until the client accepts and signs. |
| Contract | The signed agreement. | Yes. |
A proposal becomes a contract when it's signed and accepted, and the wording matters. If you want it to be a contract, put "Acceptance" and a signature line on it. If it's only a ballpark, label it "Estimate, not a binding quote". For a deeper look at estimates, see can AI write your contractor estimates.
What payment terms belong in a proposal?
A deposit at signing, draws tied to milestones, and a final payment at completion. Say how long the client has to pay each invoice. A late fee belongs there only if your state allows it and you wrote it before the work started.
Some states cap the deposit on home improvement work, so check your state's rule before you pick a number. The payment schedule template has three worked examples, at $15,000, $60,000 and $190,000.
How do you handle changes and hidden conditions?
Don't leave it to a phone call. The proposal says changes need a signed change order before the extra work starts. Then you do that, every time, even for the small stuff. The change order template has the fields and a filled example, and how to get change orders signed covers the habit.
Hidden conditions get their own clause because they feel different to the client. A change they asked for is their choice. Rot behind the siding feels like your problem. The clause tells them in advance how it works: you stop, photograph it, price it in writing.
What clauses need a lawyer?
Indemnity, arbitration, lien waivers, liquidated damages, and anything about warranty beyond "workmanship, one year". State law shapes these, and a bad clause can void the ones next to it.
Don't hire a lawyer for every job. Pay a local attorney once to review your master proposal, then reuse it. That's usually cheaper than one disputed job.
How do you get it signed?
Send it the day you walk the job, while the client still remembers you. Say when the price expires. Make signing one tap on a phone, not print, sign, scan.
Federal law, the ESIGN Act, says a signature or contract can't be denied only because it's electronic. State rules and the kind of document can add requirements, so keep a record of who signed, when, and which version they saw.
If you voice-note the job, Nailed can build the proposal for you. Here's how that goes in chat:
- You: Hendry deck. Demo 1800, 8 piers at 310, PT framing 224 sf at 16, composite decking 224 sf at 24, 44 feet of rail at 68, stairs 2100, permit 385. Draws 10/30/30/30
- Nailed: Got it. 7 lines, total $18,717.00. Payments: $1,871.70, then $5,615.10 three times. Check the lines, then tap to send. It goes to her by email with a link to sign.
- You: send it
- Nailed: Sent in your name. I'll tell you the moment she signs.
The totals come from code, not from the model, and nothing goes to the client until you tap. More in how it works, and what it costs is on the pricing page. If you want the wider picture, read about the AI office manager for contractors.
Frequently asked questions
Is a proposal legally binding once signed?
Usually, yes. When the client accepts and signs and the terms are clear, a proposal can work as the contract. Many contractors sign the proposal and skip a second document. If your state has home improvement contract rules, the proposal has to meet them. Check yours or ask a local attorney.
Should I put my license number on the proposal?
If your state licenses contractors, yes. Many states require the number on contracts and ads, and clients look for it. If you're not sure what your state requires, check with your licensing board. Insurance carrier and policy number are worth adding too.
How long should a proposal stay valid?
Fifteen to thirty days is common. Lumber, copper and appliance prices move, so a price that's good for six months is a gift to the client. Put the expiry date on the page and say what happens after: you re-price it.
What's the difference between a bid and a proposal?
A bid is mostly a price, often competitive and often for a commercial job. A proposal for a homeowner carries the price plus the scope, exclusions, schedule and terms. In practice many contractors use the words for the same document.
Can I send the proposal by text and have it signed on a phone?
Yes. Federal law says a signature can't be thrown out only because it's electronic, if the signer meant to sign. Send a PDF or a tap-to-sign link, and keep a record of who signed, when, and which version they saw.