Deck Estimate Template With a Filled 12x16 Example (Free)
Nailed writes the quote from a voice note you send from the truck. Try it free
This is a deck estimate for contractors: the document you hand a homeowner before you build, with each part priced by quantity and unit. Copy the template, then check the filled 12x16 deck, where every line and every draw adds up to the cent. Prefer a spreadsheet? Download the example as a CSV. It has the formulas, so change a quantity and the total follows.
What goes into a deck estimate?
The parts of the build, in the order you build them, each with a quantity, a unit and a price. Then the paperwork around it: permit, inspections, exclusions, payment schedule, how changes work, and how long the price holds.
A clean category list:
- Permit and drawings
- Layout and footings
- Framing (posts, beams, joists, hardware)
- Ledger and flashing, if it attaches to the house
- Decking surface
- Stairs
- Railing
- Fascia and trim
- Haul-away and cleanup
Keep footings and framing separate from the surface. When the client trades up from pressure-treated to composite, only the surface line moves.
Copy-paste deck estimate template
ESTIMATE #[number]
Date: [date] Valid until: [date, 14 to 30 days out] Contractor: [business name, phone, license # if your state requires one] Client: [name] Job address: [address]
SCOPE OF WORK [Size, height above grade, attached or free-standing, surface material, stairs, rail. Who supplies what.]
LINE ITEMS Item | Qty | Unit | Unit price | Amount Permit and drawings | [1] | LS | $[ ] | $[ ] Footings, dug, formed and poured | [ ] | ea | $[ ] | $[ ] Framing: posts, beams, joists, hardware | [ ] | sf | $[ ] | $[ ] Ledger board, flashing and fasteners | [ ] | lf | $[ ] | $[ ] Decking, supply and install (ALLOWANCE) | [ ] | sf | $[ ] | $[ ] Stairs, [number] risers, [width] wide | [1] | LS | $[ ] | $[ ] Railing, supply and install | [ ] | lf | $[ ] | $[ ] Fascia and skirt trim | [ ] | lf | $[ ] | $[ ] Haul-away and cleanup | [1] | LS | $[ ] | $[ ] TOTAL: $[ ]
ALLOWANCES Items marked ALLOWANCE are placed at the amount shown. If the final selection costs more, the difference is added by written change order before ordering. If it costs less, the difference is credited.
EXCLUSIONS (not in this price) Electrical, lighting and outlets. Rot, damage or missing flashing found behind existing siding at the ledger. Rock, ledge, buried utilities or poor soil found while digging. Grading, drainage and landscaping. Staining or sealing. Anything not listed above.
PERMITS AND INSPECTIONS [Included as a line above / the owner pulls the permit.] Inspections are scheduled by [contractor / owner].
PAYMENT SCHEDULE 10% at signing: $[ ] 40% when footings are inspected: $[ ] 30% when framing and surface are complete: $[ ] Balance at completion: $[ ]
CHANGES Any change to scope, price or schedule is agreed in writing, signed by both sides, before the work starts.
This estimate is good until [date]. It becomes a contract when both sides sign below.
Client: ______________________ Date: ________ Contractor: __________________ Date: ________
Need wording for a mid-job change, like a longer run of rail? Use the change order template. For the full contract language, see the construction proposal template.
What does a filled-in deck estimate look like?
A 12x16 deck, about 30 inches off the ground, attached to the house on one side. Nine footings, composite surface, four-step stairs, rail on three sides. These are made-up numbers to show the layout and the math. They are not a price guide, so use your own rates.
| Item | Qty | Unit | Unit price | Amount |
|---|---|---|---|---|
| Permit and drawings | 1 | LS | $450.00 | $450.00 |
| Footings, dug, formed and poured | 9 | ea | $185.00 | $1,665.00 |
| Framing: posts, beams, joists, hardware | 192 | sf | $14.50 | $2,784.00 |
| Ledger board, flashing and fasteners | 16 | lf | $22.00 | $352.00 |
| Composite decking, supply and install (ALLOWANCE) | 192 | sf | $19.00 | $3,648.00 |
| Stairs, 4 risers, 4 ft wide | 1 | LS | $1,150.00 | $1,150.00 |
| Railing, supply and install | 36 | lf | $58.00 | $2,088.00 |
| Composite fascia | 44 | lf | $9.50 | $418.00 |
| Haul-away and cleanup | 1 | LS | $380.00 | $380.00 |
| Total | $12,935.00 |
Check two: 192 sf at $14.50 is $2,784.00. 36 lf of rail at $58.00 is $2,088.00. The nine lines add to $12,935.00.
The rail run is 16 plus 12 plus 12, which is 40 feet, less a 4-foot opening for the stairs. That's 36. Write how you got the footage next to your own estimate, so you can explain it in one breath.
How do you handle the ledger and the house?
Price the ledger and flashing as their own line, and exclude what you can't see. You can't tell what's behind the siding until it's off. If the sheathing is soft or somebody skipped flashing years ago, that's a repair, and the client should hear about it before you cover it.
Should the decking be an allowance?
If the client hasn't chosen a board, yes. An allowance is a set amount in the price for something not yet picked. The client chooses. If the pick comes in over, they pay the difference. If it comes in under, they get a credit.
In the example the composite is $19.00 a square foot. A client who falls for a premium board at $26.00 adds $7.00 a square foot, which is $1,344.00 on 192 sf. Say so in writing, by change order, before you order. The change order template covers the wording.
What should you leave out of the price, and say so?
Anything you can't see or didn't price. A short list for most decks:
- Electrical, lights and outlets
- Rot or damage found behind existing siding
- Rock, ledge, buried lines or bad soil found while digging
- Grading and drainage
- Stain, seal or paint
- Anything not on the line items
An exclusion only protects you if the client saw it before they signed. Point at it when you hand over the estimate.
How should you split the payments on a deck?
Tie each draw to something the client can walk out and see. This example uses 10/40/30 and the remainder, on the $12,935.00 total:
| Draw | When | Amount |
|---|---|---|
| 1 | At signing (10%) | $1,293.50 |
| 2 | Footings inspected (40%) | $5,174.00 |
| 3 | Framing and surface complete (30%) | $3,880.50 |
| 4 | Completion (remainder) | $2,587.00 |
| Total | $12,935.00 |
Several states cap the deposit a contractor can take, so check your own rules before you set the first draw. More schedules, including a $15k job and a $60k job, are in the contractor payment schedule template.
How do you send it so it gets signed?
Make it easy to sign on a phone. A PDF the homeowner has to print, sign and scan is a week of waiting. A link they tap, read and sign is an afternoon.
Nailed works this way today. You send a voice note, Nailed drafts the quote, you read it, you tap to send, and your client gets an email with a signing link. The AI doesn't do the math. The prices are yours and the totals come from code. This is the first part of a deck, shortened, with made-up numbers.
- You: Voice note (0:24): Deck for the Okafors, 12 by 16, attached. Nine footings at 185. Framing is 192 feet at 14.50. Composite decking is an allowance, 19 a foot.
- Nailed: Got it. Draft quote, Okafor deck: Footings, 9 ea at $185.00: $1,665.00 Framing, 192 sf at $14.50: $2,784.00 Composite decking (ALLOWANCE), 192 sf at $19.00: $3,648.00 Total so far: $8,097.00 What's next? Tap Send when it's done, or keep talking.
Nothing reaches the client until you tap send. See how it works, or read the honest version of what AI can and can't do on an estimate.
Does the estimate show my markup?
No. Keep it on your cost sheet. Each line the client sees already carries it. Before you send, run the total through the markup and margin calculator so you know what the deck really makes, and see the profit margin guide for what remodelers actually keep. Working out what a day of your crew costs? Start with the loaded labor rate calculator.
Want the estimate, the signature and the payment follow-ups handled from your phone? That's what Nailed does for small contractors. Plans are on the pricing page.
Frequently asked questions
Should decking be an allowance?
If the client hasn't picked a board, yes. Composite runs from entry level to premium, and the spread per square foot is big. Set the allowance at a believable price, say who pays the difference, and settle the pick before you order.
Do I price a deck by the square foot?
As a check, yes. As the estimate, no. A flat per-square-foot number hides stairs, rail, height and footings, which swing the job more than the surface does. Price each part, then divide by the square feet to sanity-check against past decks.
Who pulls the permit for a deck?
It depends on your town. Some want the contractor, some the owner. Put a permit line on the estimate and write down who pulls it and who pays. Decks attached to a house usually need one, so ask the building department first.
How do I handle a ledger on an old house?
Price the ledger and flashing as their own line, and exclude rot or bad sheathing behind the siding. Once the siding is off you may find damage nobody could see. Quote repairs as a unit price or a change order before you cover them up.
How long should a deck estimate stay valid?
Lumber and composite prices move, so keep it short. 14 to 30 days is common. Put the date on the estimate, and say the price holds only if it's signed by then.